DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work

Project DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work
Project Code IDKGOK112217557P1
Type Package
Main Project DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work
Status On-going
District Idukki
Executing Office Nedumkandam Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1320000
TS Number WRD/KWA-CE(CR)/EST_TS/13987/2022_26_3_2
Technical specification Parappu to Marykulam-Pipeline Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/08/2023
Scheduled date of Completion as per agreement 18 Aug 2024
Expected date of Completion 17/06/2025

Processing Dates

TS Date 02 May 2023
Estimate Approval 02 May 2023
NIT Approval 02 May 2023
Tender Closing 01 Jun 2023
Technichal Pre-Qualification 02 May 2023
Price bid opening 03 Jun 2023

Approval Dates

Workorder Date 26 Jul 2023
NA 17 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nedumkandam Sn AE
Date: 21/01/2026

Work has been completed | 100% Completed

The pipeline laying work has been completed, and the house connection work for the water supply has also been completed..

Nedumkandam Sn AE
Date: 20/01/2026

Work in progress | 99% Completed

The pipeline laying work has been completed, and the house connection work for the water supply is in progress..