JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount.

Project JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount.
Project Code PKDJJM09219406P3
Type Package
Main Project JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount.
Status On-going
District Palakkad
Executing Office Cherplassery PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1406000
TS Number WRD/KWA-CE(NR)/EST_TS/22794/2023
Technical specification JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/08/2023
Scheduled date of Completion as per agreement 10 Feb 2024
Expected date of Completion 10/02/0024

Processing Dates

TS Date 22 Nov 2023
Estimate Approval 22 Nov 2023
Tender Closing 28 Nov 2023

Approval Dates

Workorder Date 13 Dec 2023
NA 19 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Cherpulassery PH Sn AE
Date: 26/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation..

Cherpulassery PH Sn AE
Date: 21/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation..