- JJM 2020 -21 -Supplying, laying, testing...
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
Project |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II |
Project Code |
PKDJJM09219406 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
83900000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
63700000 |
TS Number |
TS/2021-2022/2020/21126 |
Total Bill Submitted (Rs) |
46571977 |
Total Bill Paid (Rs) |
46571977 |
Population Benefitted |
17101 |
Capacity in MLD |
11.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
1678nos |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work |
Cherplassery PH Sn |
|
2 |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II |
Cherplassery PH Sn |
|
3 |
JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount. |
Cherplassery PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office |
Shornur PH Dn EE |
|
14 Dec 2023 |
Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. |
Cherpulassery PH Sn AE |
|
04 Dec 2023 |
Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. |
Cherpulassery PH Sn AE |
|
30 Nov 2023 |
Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. |
Cherpulassery PH Sn AE |
|
27 Nov 2023 |
Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. |
Cherpulassery PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/02/2022 |
Scheduled date of Completion of the Project |
16 Aug 2022 |
Expected date of Completion |
31/01/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
30 Nov 2021 |