Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II

Project JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
Project Code PKDJJM09219406
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 83900000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 63700000
TS Number TS/2021-2022/2020/21126
Total Bill Submitted (Rs) 46571977
Total Bill Paid (Rs) 46571977
Population Benefitted 17101
Capacity in MLD 11.00
Actual Project Completion Date Date is not specified
Coverage 1678nos
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work Cherplassery PH Sn
2 JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II Cherplassery PH Sn
3 JJM PHASE II -Supplying,laying,testing,commissioning and maintenance of distribution system Vellinezhy Panchayath phase-II -Balance work for completing FHTCs using balance amount. Cherplassery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office Shornur PH Dn EE
14 Dec 2023 Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. Cherpulassery PH Sn AE
04 Dec 2023 Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. Cherpulassery PH Sn AE
30 Nov 2023 Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. Cherpulassery PH Sn AE
27 Nov 2023 Total pipe are laid 90 mm HDPE-pipe 12120 m/12120 m ,110 mm HDPE- pipe 9090m/9090 m ,140mm HDPE - 4545(4545m), 160mm HDPE pipe - 1012m (1012m), 80 mm GI pipe-572.7 m/3000 m ,100 mm GI pipe- 60.6 m/2000m,20mm HDPE 1200 m . FHTCs given 1131nos / 1695no.s. Balance FHTC's to be given at Panchayath is 113 No.s only.An additional work for providing FHTc's (63mmpvc pipe - 9900m, 75mm pvc pipe - 1302m, 65mm GI pipe - 300m, 50mm GI pipe - 1000m) as Pipe line extension and its tender work is completed and further proceedings of this tendered work has to be completed by the Division Office. Cherpulassery PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/02/2022
Scheduled date of Completion of the Project 16 Aug 2022
Expected date of Completion 31/01/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 30 Nov 2021

Other details

Project Officers View