Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Cherpulassery PH Sn AE
Date: 01/07/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 26/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 21/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 18/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 13/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 11/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 05/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 30/05/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation.

Cherpulassery PH Sn AE
Date: 27/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 23/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 20/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 16/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 13/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 10/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 07/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 02/05/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 27/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 23/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 19/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 16/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 09/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 06/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 03/04/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 30/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 26/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 22/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 19/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 16/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 13/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 11/03/2024

Work in progress | 95% Completed

95% Work Completed.

Cherpulassery PH Sn AE
Date: 07/03/2024

Work in progress | 95% Completed

95% Work Completed

Cherpulassery PH Sn AE
Date: 04/03/2024

Work in progress | 94% Completed

94% Work Completed

Cherpulassery PH Sn AE
Date: 01/03/2024

Work in progress | 94% Completed

94% Work Completed

Cherpulassery PH Sn AE
Date: 28/02/2024

Work in progress | 93% Completed

93% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 26/02/2024

Work in progress | 93% Completed

93% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 22/02/2024

Work in progress | 92% Completed

92% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 20/02/2024

Work in progress | 92% Completed

90% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 16/02/2024

Work in progress | 92% Completed

90% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 14/02/2024

Work in progress | 90% Completed

90% WORK COMPLETED

Cherpulassery PH Sn AE
Date: 12/02/2024

Work in progress | 90% Completed

90% WORK COMPLETED

Shornur PH Dn EE
Date: 08/02/2024

Work in progress | 90% Completed

ongoing