- Home
- Jal Jeevan Mission 2021-22 ( Phase III)...
Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath
Project |
Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath |
Project Code |
TCRJJM022213940 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath |
Status |
On-going |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
201000000
|
AS Number |
G.O.(Rt)No.134/2022/WRD Dated,Thiruvananthapuram, 23-02-2022 |
TS Amount (Rs) |
162900000 |
TS Number |
TS/2022-2023/2022/20026 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
22500 |
Capacity in MLD |
33.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Providing FHTCs in Porkulam Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath |
Kunnamkulam Sn |
|
2 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS- Providing FHTCs in Porkulam Panchayath (Phase III) - Additional work-Road Restoration Work-General Civil Work |
Kunnamkulam Sn |
|
3 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS-Providing FHTCs in Porkulam Panchayath Phase III-LSGD Road Restoration Work-Additional Work II-General Civil Work |
Kunnamkulam Sn |
|
4 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS-Providing FHTCs in Porkulam Panchayath Phase III-LSGD Road Restoration Work-Additional Work III-General Civil Work |
Kunnamkulam Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
PKG-1-200mm DI laying progress.55 FHTCs Given. Work 1-LSGD road restoration started on 30-05-2024 .Work 2-LSGD road restoration started on 30-05-2024 .Work 3-LSGD road restoration started on 30-05-2024 |
Kunnamkulam PH Sn - AE |
|
24 Jun 2024 |
PKG-1-200mm DI laying progress.55 FHTCs Given. Work 1-LSGD road restoration started on 30-05-2024 .Work 2-LSGD road restoration started on 30-05-2024 .Work 3-LSGD road restoration started on 30-05-2024 |
Kunnamkulam PH Sn - AE |
|
22 Jun 2024 |
PKG-1-200mm DI laying progress.55 FHTCs Given. Work 1-LSGD road restoration started on 30-05-2024 .Work 2-LSGD road restoration started on 30-05-2024 .Work 3-LSGD road restoration started on 30-05-2024 |
Kunnamkulam PH Sn - AE |
|
21 Jun 2024 |
PKG-1-200mm DI laying progress.55 FHTCs Given. Work 1-LSGD road restoration started on 30-05-2024 .Work 2-LSGD road restoration started on 30-05-2024 .Work 3-LSGD road restoration started on 30-05-2024 |
Thrissur PH Dn EE |
|
20 Jun 2024 |
PKG-1-200mm DI laying progress.55 FHTCs Given. Work 1-LSGD road restoration started on 30-05-2024 .Work 2-LSGD road restoration started on 30-05-2024 .Work 3-LSGD road restoration started on 30-05-2024 |
Kunnamkulam PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/11/2022 |
Scheduled date of Completion of the Project |
24 Nov 2023 |
Expected date of Completion |
18/08/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
08 Jul 2022 |