Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS-Providing FHTCs in Porkulam Panchayath Phase III-LSGD Road Restoration Work-Additional Work III-General Civil Work |
---|---|
Project Code | TCRJJM022213940P3 |
Type | Package |
Main Project | Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS-Providing FHTCs in Porkulam Panchayath Phase III-LSGD Road Restoration Work-Additional Work III-General Civil Work |
Status | On-going |
District | Thrissur |
Executing Office | Kunnamkulam Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9900000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/2188/2024_5_2_1 Dated: 08-02-2024 |
Technical specification | Providing FHTCs in Porkulam Panchayath Phase III-LSGD Road Restoration Work-Additional Work III-General Civil Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 18 Aug 2024 |
Expected date of Completion | 18/08/2024 |
TS Date | 08 Feb 2024 |
---|---|
Estimate Approval | 08 Feb 2024 |
NIT Approval | 08 Feb 2024 |
Tender Closing | 15 Feb 2024 |
Technichal Pre-Qualification | 15 Feb 2024 |
Price bid opening | 16 Feb 2024 |
Workorder Date | 19 Feb 2024 |
---|---|
NA | 05 Mar 2024 |
Kunnamkulam PH Sn - AE |
Date: 28/06/2024 |
Work in progress | 6% Completed
LSGD road restoration started on 30-05-2024 .
Kunnamkulam PH Sn - AE |
Date: 27/06/2024 |
Work in progress | 6% Completed
LSGD road restoration started on 30-05-2024 .