Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS- Providing FHTCs in Porkulam Panchayath (Phase III) - Additional work-Road Restoration Work-General Civil Work |
---|---|
Project Code | TCRJJM022213940P2 |
Type | Package |
Main Project | Jal Jeevan Mission 2021-22 ( Phase III) Augmentation of PRWSS . Providing FHTCs in Porkulam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-22-Augmentation of PRWSS- Providing FHTCs in Porkulam Panchayath (Phase III) - Additional work-Road Restoration Work-General Civil Work |
Status | On-going |
District | Thrissur |
Executing Office | Kunnamkulam Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/20377/2023_5_2_1 Dated: 02-12-2023 |
Technical specification | Additional work-Road Restoration Work-General Civil Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/12/2023 |
---|---|
Scheduled date of Completion as per agreement | 25 Mar 2024 |
Expected date of Completion | 31/07/2024 |
TS Date | 02 Dec 2023 |
---|---|
Estimate Approval | 02 Dec 2023 |
NIT Approval | 04 Dec 2023 |
Tender Closing | 11 Dec 2023 |
Technichal Pre-Qualification | 11 Dec 2023 |
Price bid opening | 12 Dec 2023 |
Workorder Date | 26 Dec 2023 |
---|---|
NA | 11 Jan 2024 |
Kunnamkulam PH Sn - AE |
Date: 28/06/2024 |
Work in progress | 3% Completed
LSGD road restoration started on 30-05-2024 .
Kunnamkulam PH Sn - AE |
Date: 27/06/2024 |
Work in progress | 3% Completed
LSGD road restoration started on 30-05-2024 .