AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - POTTAMMEL ZONE-REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING BALANCE FHTC IN VARIOUS WARDS (Mayilambadi Govindapuram Valayanad Manchakkalthodu)-Pipeline Work

Project AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - POTTAMMEL ZONE-REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING BALANCE FHTC IN VARIOUS WARDS (Mayilambadi Govindapuram Valayanad Manchakkalthodu)-Pipeline Work
Project Code CLTAMRUT032313801P35
Type Package
Main Project AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - POTTAMMEL ZONE-REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING BALANCE FHTC IN VARIOUS WARDS (Mayilambadi Govindapuram Valayanad Manchakkalthodu)-Pipeline Work
Status On-going
District Kozhikkode
Executing Office Kozhikode Dist 1 Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 11870000
TS Number 9168/2023-24
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 16 Mar 2023
Expected date of Completion 31/10/2024

Processing Dates

TS Date 19 Jul 2023
Estimate Approval 19 Jul 2023
Price bid opening 19 Jul 2023

Approval Dates

Workorder Date 25 Aug 2023
NA 07 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Dist 1 Sn 2 - AE
Date: 20/06/2025

Work in progress | 40% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance..

Kozhikode Dist 1 Sn 2 - AE
Date: 28/04/2025

Work in progress | 40% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance..