| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 40% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 40% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 18/03/2025 |
Work in progress | 40% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 12/02/2025 |
Work in progress | 31% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 24/01/2025 |
Work in progress | 31% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 16/01/2025 |
Work in progress | 30% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 07/12/2024 |
Work in progress | 30% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 19/11/2024 |
Work in progress | 20% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 06/11/2024 |
Work in progress | 20% Completed
Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 26/10/2024 |
Work in progress | 20% Completed
Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work in progress | 20% Completed
Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work in progress | 20% Completed
Work in progress. PWD road cutting permission pending.
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 16% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 14% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 12% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 8% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 2% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work has started | 0% Completed
Join Inspection Completed
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
For Join Inspection
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work has started | 0% Completed
For Join Inspection
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work has started | 0% Completed
Site Handed Over