Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode Dist 1 Sn 2 - AE
Date: 20/06/2025

Work in progress | 40% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 28/04/2025

Work in progress | 40% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 18/03/2025

Work in progress | 40% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 12/02/2025

Work in progress | 31% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 24/01/2025

Work in progress | 31% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 16/01/2025

Work in progress | 30% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 07/12/2024

Work in progress | 30% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 19/11/2024

Work in progress | 20% Completed

Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.

Kozhikode Dist 1 Sn 2 - AE
Date: 06/11/2024

Work in progress | 20% Completed

Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.

Kozhikode Dist 1 Sn 2 - AE
Date: 26/10/2024

Work in progress | 20% Completed

Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.

Kozhikode Dist 1 Sn 2 - AE
Date: 22/10/2024

Work in progress | 20% Completed

Road cutting permission received. Work was unable to to start since PWD maintanance AS not received and informed to start the work only after receiving the same.

Kozhikode Dist 1 Sn 2 - AE
Date: 21/08/2024

Work in progress | 20% Completed

Work in progress. PWD road cutting permission pending.

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 16% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 14% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 12% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 8% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 2% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 11/01/2024

Work has started | 0% Completed

Join Inspection Completed

Kozhikode PH Dn EE
Date: 11/12/2023

Work has started | 0% Completed

For Join Inspection

Kozhikode PH Dn EE
Date: 28/11/2023

Work has started | 0% Completed

For Join Inspection

Kozhikode PH Dn EE
Date: 28/10/2023

Work has started | 0% Completed

Site Handed Over