Project | JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor |
---|---|
Project Code | KLMJJM08206449P3 |
Type | Package |
Main Project | JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 295480000 |
TS Number | TS/2022-2023/2022/10067 |
Technical specification | 200mm DI K9 , 160mm PVC, 140mm PVC ,110 mm PVC ,90 mm PVC |
Contractor | Sohail shamsudeen (Mob: 9809509114) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
04 Mar 2022 | Pending | Pending | Road Cut Related Risk | Chirttakonam -Panavely road | No comments available. | Pending |
04 Mar 2022 | Pending | Pending | Road Cut Related Risk | Vettikaval Sadandapuram Road | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/05/2022 |
---|---|
Scheduled date of Completion as per agreement | 01 Aug 2023 |
Expected date of Completion | 30/09/2024 |
TS Date | 23 Apr 2022 |
---|---|
Estimate Approval | 23 Apr 2022 |
NIT Approval | 23 May 2022 |
Tender Closing | 23 May 2022 |
Technichal Pre-Qualification | 14 Jun 2022 |
Price bid opening | 24 Jun 2022 |
Workorder Date | 16 Jul 2022 |
---|---|
NA | 02 Aug 2022 |
Kollam Project Dn AE |
Date: 29/06/2024 |
Kollam Project Dn AE |
Date: 28/06/2024 |
Work in progress | 85% Completed
2357 HTCS completed 81.598 km Laying completed .