JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor

Project JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor
Project Code KLMJJM08206449P3
Type Package
Main Project JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 295480000
TS Number TS/2022-2023/2022/10067
Technical specification 200mm DI K9 , 160mm PVC, 140mm PVC ,110 mm PVC ,90 mm PVC
Contractor Sohail shamsudeen (Mob: 9809509114)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
04 Mar 2022 Pending Pending Road Cut Related Risk Chirttakonam -Panavely road No comments available. Pending
04 Mar 2022 Pending Pending Road Cut Related Risk Vettikaval Sadandapuram Road No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/05/2022
Scheduled date of Completion as per agreement 01 Aug 2023
Expected date of Completion 30/09/2024

Processing Dates

TS Date 23 Apr 2022
Estimate Approval 23 Apr 2022
NIT Approval 23 May 2022
Tender Closing 23 May 2022
Technichal Pre-Qualification 14 Jun 2022
Price bid opening 24 Jun 2022

Approval Dates

Workorder Date 16 Jul 2022
NA 02 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 29/06/2024

Work in progress | 85% Completed

2357 HTCS completed 81.598 km Laying completed.

Attached images

img

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 85% Completed

2357 HTCS completed 81.598 km Laying completed .