JJM - Vettikavala Panchayath Part 1 Supplying and laying distribution network providing 3472 nos FHTCs in Zone II B

Project JJM - Vettikavala Panchayath Part 1 Supplying and laying distribution network providing 3472 nos FHTCs in Zone II B
Project Code KLMJJM08206449P1
Type Package
Main Project JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - Vettikavala Panchayath Part 1 Supplying and laying distribution network providing 3472 nos FHTCs in Zone II B
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 163560000
TS Number TS/2022-2023/2022/10068
Technical specification 350mm DI K9,250mm DI K9,200 mm DI K9, 160mm PVC , 140mm PVC, 110mm pvc , 90mm PVC
Contractor SUJAI S (Mob: 9447103109)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/05/2022
Scheduled date of Completion as per agreement 03 Aug 2023
Expected date of Completion 29/02/2024

Processing Dates

TS Date 21 Apr 2022
Estimate Approval 21 Apr 2022
NIT Approval 20 May 2022
Tender Closing 23 May 2022
Technichal Pre-Qualification 13 Jun 2022
Price bid opening 24 Jun 2022

Approval Dates

Workorder Date 16 Jul 2022
NA 04 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 29/06/2024

Work in progress | 90% Completed

3137 HTC installation & 86.371Km pipe laying(DI,PVC and GI) completed .

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 90% Completed

3137 HTC installation & 86.371Km pipe laying(DI,PVC and GI) completed .