Project | JJM KANNADI -Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath |
---|---|
Project Code | PKDJJM022214391P1 |
Type | Package |
Main Project | JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 157300000 |
TS Number | TS/WRD/KWA-CE(NR)/EST_TS/2119/2022_ |
Technical specification | Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath |
Contractor | VELAYUDHAN M (Mob: 9447335838) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 27/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 26 Mar 2024 |
Expected date of Completion | 31/12/2024 |
TS Date | 16 Dec 2022 |
---|---|
Estimate Approval | 16 Dec 2022 |
NIT Approval | 27 Mar 2023 |
Tender Closing | 13 Jan 2023 |
Technichal Pre-Qualification | 16 Jan 2023 |
Price bid opening | 17 Feb 2023 |
Workorder Date | 27 Mar 2023 |
---|---|
NA | 27 Mar 2023 |
Chittur Project Dn - AE 3 |
Date: 27/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m.
Chittur Project Dn - AE 3 |
Date: 20/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m.