JJM KANNADI -Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath

Project JJM KANNADI -Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Project Code PKDJJM022214391P1
Type Package
Main Project JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 157300000
TS Number TS/WRD/KWA-CE(NR)/EST_TS/2119/2022_
Technical specification Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Contractor VELAYUDHAN M (Mob: 9447335838)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 27/03/2023
Scheduled date of Completion as per agreement 26 Mar 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 16 Dec 2022
Estimate Approval 16 Dec 2022
NIT Approval 27 Mar 2023
Tender Closing 13 Jan 2023
Technichal Pre-Qualification 16 Jan 2023
Price bid opening 17 Feb 2023

Approval Dates

Workorder Date 27 Mar 2023
NA 27 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 15% Completed

7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m.

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 15% Completed

7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m.