JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
JJM KANNADI-Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Project Code
PKDJJM022214391
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Status
On-going
District
Palakkad
Executing Office
Chittur Project Dn
AS Amount (Rs)
159100000
AS Number
GO(RT) No 134/2022/WRD
TS Amount (Rs)
157300000
TS Number
WRD/KWA-CE(NR)/EST_TS/2119/2022_
Total Bill Submitted (Rs)
24319441
Total Bill Paid (Rs)
24319441
Population Benefitted
Capacity in MLD
9.50
Actual Project Completion Date
31 Dec 2024
Coverage
KANNADI Grama panchayath
Packages
No.
Project Name
Location
View
1
JJM KANNADI -Jal Jeevan Mission (JJM)-Providing FHTCs for Kuzhalmannam and Kannadi Grama Panchayath In Palakkad District – Kannady GP Appendix - I-Construction of 7.50 LL OHSR at Kinassery, supplying and laying balance distribution network and providing FHTCs in Kannadi grama Panchayath
Project Division Chittur
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
20 Jun 2024
Work in progress | 15% Completed | 20/06/2024
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3
12 Jun 2024
Work in progress | 15% Completed | 12/06/2024
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3
06 Jun 2024
Work in progress | 15% Completed | 06/06/2024
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3
01 Jun 2024
Work in progress | 15% Completed | 01/06/2024
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3
23 May 2024
Work in progress | 15% Completed | 23/05/2024
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m