Chittur Project Dn - AE 3 |
Date: 27/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 20/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 12/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 06/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 01/06/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 23/05/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 16/05/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 09/05/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 02/05/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 25/04/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 19/04/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 11/04/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 30/03/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-33.97KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M 5) 90mm 6kg PVC 1220m
Chittur Project Dn - AE 3 |
Date: 01/03/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-32.771KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M
Chittur Project Dn - AE 3 |
Date: 22/02/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-32.771KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M
Chittur Project Dn - AE 3 |
Date: 15/02/2024 |
Work in progress | 15% Completed
7.50 LL OHSR WORK -NOT STARTED,FHTC Work in progress Pipe line laying work 70% of work complete TOTAL-32.771KM LAID/45KM 1)90 MM PVC – 27.345 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1762M
Chittur Project Dn - AE 3 |
Date: 24/01/2024 |
Work in progress | 13% Completed
7.50 LL OHSR WORK -NOT STARTED, Pipe line laying work 70% of work complete TOTAL-32.036KM LAID/45KM 1)90 MM PVC – 26.640 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m 4) 80mm GI-1732M
Chittur Project Dn - AE 3 |
Date: 30/11/2023 |
Work in progress | 12% Completed
TOTAL-29.619KM LAID/45KM 1)90 MM PVC – 25.955 km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m
Chittur Project Dn - AE 3 |
Date: 09/11/2023 |
Work in progress | 11% Completed
TOTAL-26.914KM LAID/45KM 1)90 MM PVC – 23.250km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m
Chittur Project Dn - AE 3 |
Date: 03/11/2023 |
Work in progress | 11% Completed
TOTAL-21.359KM LAID/45KM 1)90 MM PVC – 17.695km LAID 2)110mm pvc-2951 m laid 3)160mm pvc-713m
Chittur Project Dn - AE 3 |
Date: 12/10/2023 |
Work in progress | 10% Completed
TOTAL-10.939KM LAID/45KM 90 MM PVC – 10.153km LAID 110mm pvc-786m laid
Chittur Project Dn - AE 3 |
Date: 06/10/2023 |
Work in progress | 5% Completed
90 MM PVC - 4.447M LAID /45KM
Chittur Project Dn - AE 3 |
Date: 07/09/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work in progress
Chittur Project Dn - AE 3 |
Date: 26/08/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work is in progress
Chittur Project Dn - AE 3 |
Date: 15/08/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work is in progress
Chittur Project Dn - AE 3 |
Date: 04/08/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work is in progress
Chittur Project Dn - AE 3 |
Date: 20/07/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work is in progress
Chittur Project Dn - AE 3 |
Date: 13/07/2023 |
Work in progress | 1% Completed
PVC pipes supplied on site ,pipe supply work is in progress
Chittur Project Dn - AE 3 |
Date: 06/07/2023 |
Work in progress | 1% Completed
Agreement executed