JJM-WSS to Keezhuparamba Panchayath in Malappuram District
Project |
JJM-WSS to Keezhuparamba Panchayath in Malappuram District |
Project Code |
MLPJJM022211990 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
providing FHTC in Keezhuparamba GP |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
AS Amount (Rs) |
570600000
|
AS Number |
Go (rt) 134/2022 WRd |
TS Amount (Rs) |
508890000 |
TS Number |
9330/2022 |
Total Bill Submitted (Rs) |
164124570 |
Total Bill Paid (Rs) |
77866260 |
Population Benefitted |
35894 |
Capacity in MLD |
5.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
keezhuparamba grama panch |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM -WSS to Keezuparamba Panchayth in Malappuram Dt-Packakage III- Replacing existing 200mm DI Raw water pumping main with 300mm DI K9 ,Genaral maintenance work of existing Intake well cum pump house including supply erection testing commissioning of Raw water and clear water pump sets and transformers -General Civil Work |
Project Division Malappuram |
|
2 |
Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR |
Project Division Malappuram |
|
3 |
Package IV- LSGD Road restoration work including- providing additional FHTC |
Project Division Malappuram |
|
4 |
Pckage 1-Construction of 5 MLD WTP ,with sump cum pump house ,8.5l0 LL OHSR at WTP site |
Project Division Malappuram |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 May 2024 |
Pckage 1-Construction of 5 MLD WTP ,with sump cum pump house ,8.5l0 LL OHSR at WTP site- Septic tank work.Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR- Ward 5 forest road 80 mm GI work. JJM -WSS to Keezuparamba Panchayth in Malappuram Dt-Packakage III- Replacing existing 200mm DI Raw water pumping main with 300mm DI K9 ,Genaral maintenance work of existing Intake well cum pump house including supply erection testing commissioning of Raw water and clear water pump sets and transformers -General Civil Work-Work not started Package IV- LSGD Road restoration work including- providing additional FHTC- Work not started |
Malappuram Project Dn AE6 |
|
14 Feb 2024 |
Pckage 1-Construction of 5 MLD WTP ,with sump cum pump house ,8.5l0 LL OHSR at WTP site-Boundary wall work
Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR- Thrikkalayoor Pannicode road 63mm PVC work& road cutting.ward 13 saddle
Jal Jeevan Mission (JJM)-JJM -WSS to Keezuparamba Panchayth in Malappuram Dt-Packakage III- Replacing existing 200mm DI Raw water pumping main with 300mm DI K9 ,Genaral maintenance work of existing Intake well cum pump house including supply erection testing commissioning of Raw water and clear water pump sets and transformers -General Civil Work-Work not started
Package IV- LSGD Road restoration work including- providing additional FHTC- Work not started
|
Malappuram Project Dn AE6 |
|
25 Oct 2023 |
Pckage 1- OH Tank Hand rail work, OH Tank painting work, pipe gallery tile work
Package II -Concrete breaking & saddling work, 300mm Di, 150mm Di, 90mm hdp rider pipe works are on going
|
Malappuram Project Dn AE6 |
|
04 Jul 2023 |
Package II-Pipe Gallery Mechanical work, Ground Floor Masonry, OH Tank slab steel work.
Package I-OH Tank slab steel work
|
Malappuram Project Dn AE6 |
|
15 Jun 2023 |
Quarry muck fill with Trench & site clearing and OHT Third floor beam shuttering, OHT Pipe Gallery work, OHT Alum Lime Plastering.
|
Malappuram Project Dn AE6 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/08/2022 |
Scheduled date of Completion of the Project |
15 Aug 2023 |
Expected date of Completion |
14/02/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
10 Aug 2023 |