20 May 2024 Pckage 1-Construction of 5 MLD WTP ,with sump cum pump house ,8.5l0 LL OHSR at WTP site- Septic tank work.Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR- Ward 5 forest road 80 mm GI work. JJM -WSS to Keezuparamba Panchayth in Malappuram Dt-Packakage III- Replacing existing 200mm DI Raw water pumping main with 300mm DI K9 ,Genaral maintenance work of existing Intake well cum pump house including supply erection testing commissioning of Raw water and clear water pump sets and transformers -General Civil Work-Work not started Package IV- LSGD Road restoration work including- providing additional FHTC- Work not started Malappuram Project Dn AE6
14 Feb 2024 Pckage 1-Construction of 5 MLD WTP ,with sump cum pump house ,8.5l0 LL OHSR at WTP site-Boundary wall work Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR- Thrikkalayoor Pannicode road 63mm PVC work& road cutting.ward 13 saddle Jal Jeevan Mission (JJM)-JJM -WSS to Keezuparamba Panchayth in Malappuram Dt-Packakage III- Replacing existing 200mm DI Raw water pumping main with 300mm DI K9 ,Genaral maintenance work of existing Intake well cum pump house including supply erection testing commissioning of Raw water and clear water pump sets and transformers -General Civil Work-Work not started Package IV- LSGD Road restoration work including- providing additional FHTC- Work not started Malappuram Project Dn AE6
25 Oct 2023 Pckage 1- OH Tank Hand rail work, OH Tank painting work, pipe gallery tile work Package II -Concrete breaking & saddling work, 300mm Di, 150mm Di, 90mm hdp rider pipe works are on going Malappuram Project Dn AE6
04 Jul 2023 Package II-Pipe Gallery Mechanical work, Ground Floor Masonry, OH Tank slab steel work. Package I-OH Tank slab steel work Malappuram Project Dn AE6
15 Jun 2023 Quarry muck fill with Trench & site clearing and OHT Third floor beam shuttering, OHT Pipe Gallery work, OHT Alum Lime Plastering. Malappuram Project Dn AE6
11 May 2023 Package ll-200mm DI & 90mm HDP Layed in Pottammal -Trikkalayoor PWD road, 90mm HDP Layed ward 3& ward 13, compound wall work Thadaparamb Tank Package l- OHT second floor slab steel work. Malappuram Project Dn AE6
05 May 2023 160mm HDP Laying in Trikkalayoor -Pottammal Pwd road, plastering work at Thadaparamb Tank.Oothupallipurai branch road 90mm HDP Laying and Clarifair slab work Malappuram Project Dn AE6
20 Apr 2023 Prabhad branch road 90mm HDP Laying, Celing Plastering Thadaparamb Tank, road cutting to use meashine.and OHT second floor slab shuttering work, Clarifair work. Malappuram Project Dn AE6
10 Apr 2023 Ward 14 Kinattinkandi road & ward 2 valachatti potta road 90 mm HDP Laying,curing of slab & hand rail Thadaparamb Tank. And Solution room slab concrete, Launder channel shuttering work, Malappuram Project Dn AE6
02 Apr 2023 Ongoing Malappuram Project Dn AE6