Project | Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR |
---|---|
Project Code | MLPJJM022211990P2 |
Type | Package |
Main Project | JJM-WSS to Keezhuparamba Panchayath in Malappuram District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Package II - Supply Laying ,Distribution System with FHTC & 4.00LL OHSR |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 287606495 |
TS Number | 3523/22-23 |
Technical specification | Providing FHTC |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/08/2022 |
---|---|
Scheduled date of Completion as per agreement | 15 Aug 2022 |
Expected date of Completion | 31/08/2023 |
TS Date | 12 May 2022 |
---|
Workorder Date | 16 Aug 2022 |
---|---|
NA | 31 Aug 2022 |
Malappuram Project Dn AE6 |
Date: 28/06/2024 |
Malappuram Project Dn AE6 |
Date: 27/06/2024 |
Work in progress | 80% Completed