Jal Jeevan Mission -Providing FHTC to Adichanalloor panchayath-Phase II

Project Jal Jeevan Mission -Providing FHTC to Adichanalloor panchayath-Phase II
Project Code KLMJJM022214298
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction of 5LL OHSR at Kattachal junction after Demolishing existing OHSR,Providing 300mm DI K9 Distribution Line after replacing existing AC line and Providing rider line of 160mm UPVC 10kg pipe.
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 66500000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 49200000
TS Number TS/5087/2022
Total Bill Submitted (Rs) 15944780
Total Bill Paid (Rs) 15944780
Population Benefitted 31258
Capacity in MLD 7.50
Actual Project Completion Date 17 Sep 2023
Coverage Adichanalloor Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission-Providing FHTC to Adichanalloor Panchayath-Phase II Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1987.1m/2000m) and 160mm 10kg pvc rider line(2853.05m/3200m) pipe laying in progress. Kollam Project Dn EE
09 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2627.45m/3200m) pipe laying in progress. Kollam Project HD
08 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2626.45m/3200m) pipe laying in progress. Kollam Project HD
07 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1957.85m/2000m) and 160mm 10kg pvc rider line(2621.85m/3200m) pipe laying in progress. Kollam Project HD
05 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1928.2m/2000m) and 160mm 10kg pvc rider line(2587.85m/3200m) pipe laying in progress. Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/03/2023
Scheduled date of Completion of the Project 17 Sep 2023
Expected date of Completion 17/09/2023

Processing Dates

AS Date 23 Feb 2022
TS Date 24 Jan 2023