- Home
- Jal Jeevan Mission -Providing FHTC to Ad...
Jal Jeevan Mission -Providing FHTC to Adichanalloor panchayath-Phase II
Project |
Jal Jeevan Mission -Providing FHTC to Adichanalloor panchayath-Phase II |
Project Code |
KLMJJM022214298 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction of 5LL
OHSR at Kattachal junction after Demolishing
existing OHSR,Providing 300mm DI K9
Distribution Line after replacing existing AC
line and Providing rider line of 160mm UPVC
10kg pipe. |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
66500000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
49200000 |
TS Number |
TS/5087/2022 |
Total Bill Submitted (Rs) |
15944780 |
Total Bill Paid (Rs) |
15944780 |
Population Benefitted |
31258 |
Capacity in MLD |
7.50 |
Actual Project Completion Date |
17 Sep 2023 |
Coverage |
Adichanalloor Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission-Providing FHTC to Adichanalloor Panchayath-Phase II |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Jan 2024 |
All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1987.1m/2000m) and 160mm 10kg pvc rider line(2853.05m/3200m) pipe laying in progress.
|
Kollam Project Dn EE |
|
09 Jan 2024 |
All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2627.45m/3200m) pipe laying in progress.
|
Kollam Project HD |
|
08 Jan 2024 |
All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2626.45m/3200m) pipe laying in progress.
|
Kollam Project HD |
|
07 Jan 2024 |
All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1957.85m/2000m) and 160mm 10kg pvc rider line(2621.85m/3200m) pipe laying in progress.
|
Kollam Project HD |
|
05 Jan 2024 |
All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1928.2m/2000m) and 160mm 10kg pvc rider line(2587.85m/3200m) pipe laying in progress.
|
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/03/2023 |
Scheduled date of Completion of the Project |
17 Sep 2023 |
Expected date of Completion |
17/09/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
24 Jan 2023 |