Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1987.1m/2000m) and 160mm 10kg pvc rider line(2853.05m/3200m) pipe laying in progress. Kollam Project Dn EE
09 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2627.45m/3200m) pipe laying in progress. Kollam Project HD
08 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2626.45m/3200m) pipe laying in progress. Kollam Project HD
07 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1957.85m/2000m) and 160mm 10kg pvc rider line(2621.85m/3200m) pipe laying in progress. Kollam Project HD
05 Jan 2024 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1928.2m/2000m) and 160mm 10kg pvc rider line(2587.85m/3200m) pipe laying in progress. Kollam Project HD
05 Dec 2023 All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI and 160mm 10kg pvc rider line pipe laying in progress. Kollam Project Dn EE
04 Dec 2023 Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress. Valve chamber concreting works completed. 300mm DI and 160mm 10kg pvc rider line pipe laying in progress. Kollam Project Dn EE
03 Dec 2023 Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress Kollam Project Dn EE
02 Dec 2023 Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress Kollam Project Dn EE
01 Dec 2023 Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering work started Kollam Project Dn EE