Project | Jal Jeevan Mission-Providing FHTC to Adichanalloor Panchayath-Phase II |
---|---|
Project Code | KLMJJM022214298P1 |
Type | Package |
Main Project | Jal Jeevan Mission -Providing FHTC to Adichanalloor panchayath-Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Construction of 5LL OHSR at Kattachal junction after Demolishing existing OHSR,Providing 300mm DI K9 Distribution Line after replacing existing AC line and Providing rider line of 160mm UPVC 10kg pipe. |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 49200000 |
TS Number | TS/5087/2022 |
Technical specification | Supply and laying of PVC Pipe, 8kg/cm2, 200mm Dia- 250m Supply and laying of PVC Pipe, 10kg/cm2, 160mm Dia-3200m Supply and laying of PVC Pipe, 10kg/cm2, 110mm Dia.-500m Supply and laying of PVC Pipe, 8kg/cm2, 50mm Dia-1000m Supply and laying of DI K9 Pipe-2000m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 17 Sep 2023 |
Expected date of Completion | 17/09/2023 |
TS Date | 24 Jan 2023 |
---|---|
Estimate Approval | 24 Jan 2023 |
NIT Approval | 07 Feb 2023 |
Tender Closing | 07 Feb 2023 |
Price bid opening | 08 Feb 2023 |
Workorder Date | 06 Mar 2023 |
---|---|
NA | 18 Mar 2023 |
Kollam Project HD |
Date: 27/06/2024 |
Work has been completed | 100% Completed
Work completed. Final bill submitted and uploaded in PFMS.
Kollam Project Dn EE |
Date: 23/06/2024 |
Work in progress | 98% Completed
Total connection completed = 304/500, Total pipe Laid 50mm/8kg = 1022.5/1000m, 200mm/8kg = 246/250m , 110mm/10kg =499.6 / 500m, 160mm/ 10kg = 2871.05/ 3200m, 300mm/K9 =1996.3/2000m .