Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc

Project KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc
Project Code PKDKIIFB1118675P1
Type Package
Main Project Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 226000000
TS Number TS/2018-2019/2018/11231,dated 21.02.2019
Technical specification Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM - 15570 m &150 mm DI CWPM - 1000m, linking works etc
Contractor Joseph John (Mob: 9447267097)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/06/2019
Scheduled date of Completion as per agreement 23 Dec 2020
Expected date of Completion 31/12/2022

Processing Dates

TS Date 21 Feb 2019
Estimate Approval 21 Feb 2019
NIT Approval 18 Mar 2019
Tender Closing 25 Mar 2019
Technichal Pre-Qualification 16 Apr 2019
Price bid opening 28 Mar 2019

Approval Dates

NA 08 Jul 2019
Workorder Date 24 Jun 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 4
Date: 10/02/2023

Work in progress | 100% Completed

pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done.

Chittur Project Dn - AE 4
Date: 03/02/2023

Work in progress | 98% Completed

pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done.