KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc
Project |
KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc |
Project Code |
PKDKIIFB1118675P1 |
Type |
Package |
Main Project |
Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc
|
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
226000000 |
TS Number |
TS/2018-2019/2018/11231,dated 21.02.2019 |
Technical specification |
Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM - 15570 m &150 mm DI CWPM - 1000m, linking works etc
|
Contractor |
Joseph John (Mob: 9447267097) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
24/06/2019 |
Scheduled date of Completion as per agreement |
23 Dec 2020 |
Expected date of Completion |
31/12/2022 |
Processing Dates
TS Date |
21 Feb 2019 |
Estimate Approval |
21 Feb 2019 |
NIT Approval |
18 Mar 2019 |
Tender Closing |
25 Mar 2019 |
Technichal Pre-Qualification |
16 Apr 2019 |
Price bid opening |
28 Mar 2019 |
Approval Dates
NA |
08 Jul 2019 |
Workorder Date |
24 Jun 2019 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chittur Project Dn - AE 4 |
Date: 10/02/2023 |
Work in progress | 100% Completed
pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done.
Chittur Project Dn - AE 4 |
Date: 03/02/2023 |
Work in progress | 98% Completed
pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done.