Sl.No. | Component | Description |
---|---|---|
1 | Construction of WTP | 1. Construction of 8 MLD WTP excluding sump 2. Aerator ,Flash Mixer,Clarifoculator,FILTER HOUSE, CHEMICAL HOUSE & WASH WATER TANK,Supply of Mechanical and Electrical items,pump house |
2 | CWPM | 1. Suppliyng and laying CWPM from WTP to proposed 11 LL OHSR at Ozhalapathy, branching from proposed OHSR to existing OHSR at Ozhalapathy, linking works at WTP compound ,Supplying and laying 2. CWGM from existing Ozhalapathy OHSR to existing OHSR Polippara |
3 | Construction of OHSRS and sump | Construction of 9.80 LL OHSR at Moonkilmada,Construction of 6.00 LL clear water sump in WTP compound at Moonkilmada, |
4 | Road restoration work | Road restoration work PWD Roads and PMGSY roads |
5 | supply of 300 mm DI K9 pipe | 16037m |
6 | supply of 500 mm DI K9 pipe | 75 m |
7 | supply of 250mm DI K9 pipe | 155 m |
8 | supply of 200 mm DI K9 pipe | 20m |
9 | supply of 150 mm DI K9 pipe | 1030m |
10 | supply of 300 mm dia 10 mm thick ER welded-MS pipe | 240m |
11 | Suppliyng and laying CWPM from WTP to proposed 11 LL OHSR at Ozhalapathy, branching from proposed OHSR to existing OHSR at Ozhalapathy, linking works at WTP compound , | 300,500,250,200,150 mm dia DI K9 PIPES |
12 | Supplying and Laying CWGM from existing Ozhalapathy OHSR to existing OHSR Polippara | 150 mm DI K9 pipe-4547m |