Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
Project |
Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I |
Project Code |
PKDKIIFB1118675 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Package I
1. Construction of 8 MLD WTP
2. Construction of 9.8 LL OHSR
3. Supplying and laying CWPM 300 mm DI - 15570m and 150 mm DI - 1000m
Package II
Design , Construction, Commissioning and Maintenance of 11LL OHSR at Ozhalappathy in Vadakarappathy Panchayath |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
247700000
|
AS Number |
WRD -025-32-PA-01 OF 2018-2019 |
TS Amount (Rs) |
226000000 |
TS Number |
2018-19/2018/11231 |
Total Bill Submitted (Rs) |
177385422 |
Total Bill Paid (Rs) |
177385422 |
Population Benefitted |
95472 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
21 Jan 2021 |
Coverage |
kozhijampara ,vadakarapathy,Eruthempathy |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc |
Project Division Chittur |
|
2 |
KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Mar 2023 |
WTP-COMMISIONED ON 07.01.20202
WORK COMPLETED ON 15.11.2022 |
Chittur Project Dn - AE 4 |
|
13 Mar 2023 |
work completed |
Chittur Project Dn - AE 4 |
|
09 Mar 2023 |
Work in progress | 98% Completed | 09/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done |
Chittur Project Dn - AE 4 |
|
05 Mar 2023 |
Work in progress | 98% Completed | 05/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done |
Chittur Project Dn - AE 4 |
|
24 Feb 2023 |
Work in progress | 98% Completed | 24/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done |
Chittur Project Dn - AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/06/2019 |
Scheduled date of Completion of the Project |
28 Feb 2021 |
Expected date of Completion |
31/10/2022 |
Processing Dates
AS Date |
27 Nov 2018 |
TS Date |
21 Feb 2019 |