Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I

Project Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
Project Code PKDKIIFB1118675
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Package I 1. Construction of 8 MLD WTP 2. Construction of 9.8 LL OHSR 3. Supplying and laying CWPM 300 mm DI - 15570m and 150 mm DI - 1000m Package II Design , Construction, Commissioning and Maintenance of 11LL OHSR at Ozhalappathy in Vadakarappathy Panchayath
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 247700000
AS Number WRD -025-32-PA-01 OF 2018-2019
TS Amount (Rs) 226000000
TS Number 2018-19/2018/11231
Total Bill Submitted (Rs) 177385422
Total Bill Paid (Rs) 177385422
Population Benefitted 95472
Capacity in MLD 8.00
Actual Project Completion Date 21 Jan 2021
Coverage kozhijampara ,vadakarapathy,Eruthempathy
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc Project Division Chittur
2 KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Mar 2023 WTP-COMMISIONED ON 07.01.20202 WORK COMPLETED ON 15.11.2022 Chittur Project Dn - AE 4
13 Mar 2023 work completed Chittur Project Dn - AE 4
09 Mar 2023 Work in progress | 98% Completed | 09/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
05 Mar 2023 Work in progress | 98% Completed | 05/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
24 Feb 2023 Work in progress | 98% Completed | 24/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/06/2019
Scheduled date of Completion of the Project 28 Feb 2021
Expected date of Completion 31/10/2022

Processing Dates

AS Date 27 Nov 2018
TS Date 21 Feb 2019

Other details