AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-PROVIDING FHTCs IN BEYPORE ZONE -Pipeline Work

Project AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-PROVIDING FHTCs IN BEYPORE ZONE -Pipeline Work
Project Code CLTAMRUT032313801P13
Type Package
Main Project AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-PROVIDING FHTCs IN BEYPORE ZONE -Pipeline Work
Status On-going
District Kozhikkode
Executing Office Beypore RWS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 37300000
TS Number 16702/2022-2023
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 17/05/2024

Processing Dates

TS Date 18 Mar 2023
Estimate Approval 18 Mar 2023
NIT Approval 18 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 98% Completed

Work in progress.

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 93% Completed

Work in progress.