| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 98% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 93% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 90% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 87% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 85% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 82% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 80% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 65% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 58% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 52% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 50% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 45% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 32% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 30% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 20% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work in progress | 10% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work in progress | 2% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 25/05/2023 |
Work in progress | 1% Completed
Agreement Executed