Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs

Project Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs
Project Code PKDJJM022214418
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 412200000
AS Number GO (RT) no 134/WRD dtd 23.02.2022
TS Amount (Rs) 408400000
TS Number ORDER No.: WRD/KWA-CEP/EST_TS/134/2022 26 1_1 Dated: 06-12-2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 26669
Capacity in MLD
Actual Project Completion Date 31 Dec 2024
Coverage THARUR

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs -Pipeline Work Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 12% Completed | 20/06/2024 90MM Pipe laid for a length of 20.38 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-6946 m 2).90mm PVC 8 kg-11546 m 3).110 mm pvc 10 kg-1548 m 4) 90mm PVC 6 kg = 204 m 5) 110 mm pvc 8 kg = 144 m Chittur Project Dn - AE 3
12 Jun 2024 Work in progress | 12% Completed | 12/06/2024 90MM Pipe laid for a length of 20.74 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-6208m 2).90mm PVC 8 kg-11282m 3).110 mm pvc 10 kg-1476m 4) 90mm PVC 6 kg = 204m 5) 110 mm pvc 8 kg = 144m Chittur Project Dn - AE 3
06 Jun 2024 Work in progress | 12% Completed | 06/06/2024 90MM Pipe laid for a length of 20.74 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-10928m 3).110 mm pvc 10 kg-1476m 4) 90mm PVC 6 kg = 204m 5) 110 mm pvc 8 kg = 144m Chittur Project Dn - AE 3
01 Jun 2024 Work in progress | 11% Completed | 01/06/2024 90MM Pipe laid for a length of 19.564 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-10122m 3).110 mm pvc 10 kg-1248m 4) 90mm PVC 6 kg = 204m Chittur Project Dn - AE 3
23 May 2024 Work in progress | 11% Completed | 23/05/2024 90MM Pipe laid for a length of 19 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-9762m 3).110 mm pvc 10 kg-1248m Chittur Project Dn - AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/05/2023
Scheduled date of Completion of the Project 23 May 2024
Expected date of Completion 23/05/2024

Processing Dates

AS Date 23 Feb 2023
TS Date 06 Dec 2022