Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs -Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs -Pipeline Work
Project Code PKDJJM022214418P1
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs -Pipeline Work
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 408400000
TS Number ORDER No.: WRD/KWA-CEP/EST_TS/134/2022_26_1_1 Dated: 06-12-2022
Technical specification Jal Jeevan Mission (JJM)-JJM-Tarur grama panchayath -JJM-Supplying and laying Distribution system and providing FHTCs -
Contractor C T Thambi (Mob: 9495321861)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/05/2023
Scheduled date of Completion as per agreement 23 May 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 06 Dec 2022
Estimate Approval 06 Dec 2022
NIT Approval 24 May 2023
Tender Closing 06 Mar 2023
Technichal Pre-Qualification 16 Mar 2023
Price bid opening 07 Mar 2023

Approval Dates

Workorder Date 24 May 2023
NA 24 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 14% Completed

90MM Pipe laid for a length of 22.21KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg- 7960 m 2).90mm PVC 8 kg-11546 m 3).110 mm pvc 10 kg-1548 m 4) 90mm PVC 6 kg = 204 m 5) 110 mm pvc 8 kg = 960 m .

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 12% Completed

90MM Pipe laid for a length of 20.38 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-6946 m 2).90mm PVC 8 kg-11546 m 3).110 mm pvc 10 kg-1548 m 4) 90mm PVC 6 kg = 204 m 5) 110 mm pvc 8 kg = 144 m .