Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Jun 2024 |
Work in progress | 14% Completed | 27/06/2024
90MM Pipe laid for a length of 22.21KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg- 7960 m 2).90mm PVC 8 kg-11546 m 3).110 mm pvc 10 kg-1548 m 4) 90mm PVC 6 kg = 204 m 5) 110 mm pvc 8 kg = 960 m |
Chittur Project Dn - AE 3 |
|
20 Jun 2024 |
Work in progress | 12% Completed | 20/06/2024
90MM Pipe laid for a length of 20.38 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-6946 m 2).90mm PVC 8 kg-11546 m 3).110 mm pvc 10 kg-1548 m 4) 90mm PVC 6 kg = 204 m 5) 110 mm pvc 8 kg = 144 m |
Chittur Project Dn - AE 3 |
|
12 Jun 2024 |
Work in progress | 12% Completed | 12/06/2024
90MM Pipe laid for a length of 20.74 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-6208m 2).90mm PVC 8 kg-11282m 3).110 mm pvc 10 kg-1476m 4) 90mm PVC 6 kg = 204m 5) 110 mm pvc 8 kg = 144m |
Chittur Project Dn - AE 3 |
|
06 Jun 2024 |
Work in progress | 12% Completed | 06/06/2024
90MM Pipe laid for a length of 20.74 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-10928m 3).110 mm pvc 10 kg-1476m 4) 90mm PVC 6 kg = 204m 5) 110 mm pvc 8 kg = 144m |
Chittur Project Dn - AE 3 |
|
01 Jun 2024 |
Work in progress | 11% Completed | 01/06/2024
90MM Pipe laid for a length of 19.564 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-10122m 3).110 mm pvc 10 kg-1248m 4) 90mm PVC 6 kg = 204m |
Chittur Project Dn - AE 3 |
|
23 May 2024 |
Work in progress | 11% Completed | 23/05/2024
90MM Pipe laid for a length of 19 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-9762m 3).110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|
16 May 2024 |
Work in progress | 11% Completed | 16/05/2024
90MM Pipe laid for a length of 17.466 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-8610m 3).110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|
09 May 2024 |
Work in progress | 11% Completed | 09/05/2024
90MM Pipe laid for a length of 16.188 KM /150km, (total FHTC 3155 to be provided) 1). 90 mm pvc 10 kg-5476m 2).90mm PVC 8 kg-7332m 3).110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|
02 May 2024 |
Work in progress | 10% Completed | 02/05/2024
90MM Pipe laid for a length of 14.188 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-4288m 2.90mm PVC 8 kg-5904m 3.110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|
25 Apr 2024 |
Work in progress | 10% Completed | 25/04/2024
90MM Pipe laid for a length of 14.188 KM /150km, (total FHTC 3155 to be provided) 1. 90 mm pvc 10 kg-4288m 2.90mm PVC 8 kg-5904m 3.110 mm pvc 10 kg-1248m |
Chittur Project Dn - AE 3 |
|