| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT -Providing FHTC By Extension And Replacing Pipeline At Revenue Ward -2,34-Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P16 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT -Providing FHTC By Extension And Replacing Pipeline At Revenue Ward -2,34-Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 2 Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 31400000 |
| TS Number | 17992/2022-2023 |
| Technical specification | FHTCs Proposed-1100nos 110mm PVC-3840m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 05 Jun 2024 |
| Expected date of Completion | 31/07/2024 |
| TS Date | 31 Mar 2023 |
|---|---|
| Estimate Approval | 31 Mar 2023 |
| NIT Approval | 31 Mar 2023 |
| NA | 20 May 2023 |
|---|
| Kozhikode PH Dn EE |
| Date: 23/10/2024 |
Work has been completed | 100% Completed
Work Completed. FHTCs provided-919 nos, Changing Connections-71 nos and 110mm PVC -3811.8m.
| Kozhikode PH Dn EE |
| Date: 22/10/2024 |
Work in progress | 98% Completed
changing connection in progress.