| Kozhikode PH Dn EE |
| Date: 23/10/2024 |
Work has been completed | 100% Completed
Work Completed. FHTCs provided-919 nos, Changing Connections-71 nos and 110mm PVC -3811.8m
| Kozhikode PH Dn EE |
| Date: 22/10/2024 |
Work in progress | 98% Completed
changing connection in progress
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work in progress | 98% Completed
changing connection in progress
| Kozhikode PH Dn EE |
| Date: 19/10/2024 |
Work in progress | 98% Completed
changing connection in progress
| Kozhikode PH Dn EE |
| Date: 18/10/2024 |
Work in progress | 98% Completed
changing connection in progress
| Kozhikode PH Dn EE |
| Date: 17/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 16/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 15/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 12/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 11/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 09/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 08/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 05/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 04/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 01/10/2024 |
Work in progress | 97% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 28/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 27/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 26/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 25/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 24/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 23/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work in progress | 96% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 18/09/2024 |
| Kozhikode PH Dn EE |
| Date: 13/09/2024 |
| Kozhikode PH Dn EE |
| Date: 12/09/2024 |
Work in progress | 95% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 11/09/2024 |
Work in progress | 95% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work in progress | 95% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 09/09/2024 |
Work in progress | 95% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 94% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 19/08/2024 |
Work in progress | 94% Completed
Restoration work in progress. FHTcs work and pipe laying work completed
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work in progress | 94% Completed
Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 26/06/2024 |
Work in progress | 91% Completed
Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 25/06/2024 |
Work in progress | 91% Completed
Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 91% Completed
Restoration work in progress
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 90% Completed
Work in progress. Pipe laid-110mm PVC-3811.8m, FHTCs-665 nos.
| Kozhikode PH Dn EE |
| Date: 30/04/2024 |
Work in progress | 77% Completed
Work in Progress-Pipe laid-2.4km, FHTCs-610 nos.
| Kozhikode PH Dn EE |
| Date: 29/04/2024 |
Work in progress | 77% Completed
Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.
| Kozhikode PH Dn EE |
| Date: 27/04/2024 |
Work in progress | 77% Completed
Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.
| Kozhikode PH Dn EE |
| Date: 26/04/2024 |
Work in progress | 77% Completed
Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 72% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 67% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work in progress | 65% Completed
pipe laid-1.25km, FHTCs-278 nos.
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work in progress | 64% Completed
pipe laid-1.25km, FHTCs-278 nos.
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 63% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 60% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 08/01/2024 |
Work in progress | 49% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 49% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 49% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 49% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 49% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 48% Completed
Work in Progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 48% Completed
Work in progress-Pipe laid-570m, FHTC-194, Tagged-84 nos. HTC-52
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 45% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 20/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 18/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 17/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 16/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 15/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 14/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 13/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 11/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 10/11/2023 |
Work in progress | 42% Completed
Work in progress. FHTC-172, HTC-34, Pipe laid-570m
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 42% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 40% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 35% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 26% Completed
Pipe laying work in progress.
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 25% Completed
Pipe laying work in progress.
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 10% Completed
Pipe laying work in progress.
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work in progress | 4% Completed
Pipe laying work in progress. HTC Provided-15 nos. Reinstating House Connections-8 nos.
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work in progress | 3% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 18/07/2023 |
Work in progress | 1% Completed
pIPE LAYING STARTED-110MM PVC-70M
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Pipe supplied
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work has started | 0% Completed
Pipe supplied
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Pipe supplied
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Pipe supplied
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 07/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 25/05/2023 |
Work in progress | 1% Completed
Agreement Executed