All updates

Kozhikode PH Dn EE
Date: 23/10/2024

Work has been completed | 100% Completed

Work Completed. FHTCs provided-919 nos, Changing Connections-71 nos and 110mm PVC -3811.8m

Kozhikode PH Dn EE
Date: 22/10/2024

Work in progress | 98% Completed

changing connection in progress

Kozhikode PH Dn EE
Date: 21/10/2024

Work in progress | 98% Completed

changing connection in progress

Kozhikode PH Dn EE
Date: 19/10/2024

Work in progress | 98% Completed

changing connection in progress

Kozhikode PH Dn EE
Date: 18/10/2024

Work in progress | 98% Completed

changing connection in progress

Kozhikode PH Dn EE
Date: 17/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 16/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 15/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 14/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 12/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 11/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 10/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 09/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 08/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 07/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 05/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 04/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 03/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 01/10/2024

Work in progress | 97% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 30/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 28/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 27/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 26/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 25/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 24/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 23/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 20/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 19/09/2024

Work in progress | 96% Completed

8547593882

Attached images

img

Kozhikode PH Dn EE
Date: 18/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Attached images

img

Kozhikode PH Dn EE
Date: 13/09/2024

Work in progress | 96% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Attached images

img

Kozhikode PH Dn EE
Date: 12/09/2024

Work in progress | 95% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 11/09/2024

Work in progress | 95% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 10/09/2024

Work in progress | 95% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 09/09/2024

Work in progress | 95% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 21/08/2024

Work in progress | 94% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 19/08/2024

Work in progress | 94% Completed

Restoration work in progress. FHTcs work and pipe laying work completed

Kozhikode PH Dn EE
Date: 16/08/2024

Work in progress | 94% Completed

Restoration work in progress

Kozhikode PH Dn EE
Date: 26/06/2024

Work in progress | 91% Completed

Restoration work in progress

Kozhikode PH Dn EE
Date: 25/06/2024

Work in progress | 91% Completed

Restoration work in progress

Kozhikode PH Dn EE
Date: 24/06/2024

Work in progress | 91% Completed

Restoration work in progress

Kozhikode PH Dn EE
Date: 14/06/2024

Work in progress | 90% Completed

Work in progress. Pipe laid-110mm PVC-3811.8m, FHTCs-665 nos.

Kozhikode PH Dn EE
Date: 30/04/2024

Work in progress | 77% Completed

Work in Progress-Pipe laid-2.4km, FHTCs-610 nos.

Kozhikode PH Dn EE
Date: 29/04/2024

Work in progress | 77% Completed

Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.

Kozhikode PH Dn EE
Date: 27/04/2024

Work in progress | 77% Completed

Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.

Kozhikode PH Dn EE
Date: 26/04/2024

Work in progress | 77% Completed

Work in Progress-Pipe laid-2.4km, FHTCs-605 nos.

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 75% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 72% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 67% Completed

Work in progress

Kozhikode PH Dn EE
Date: 05/03/2024

Work in progress | 65% Completed

pipe laid-1.25km, FHTCs-278 nos.

Kozhikode PH Dn EE
Date: 02/03/2024

Work in progress | 64% Completed

pipe laid-1.25km, FHTCs-278 nos.

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 63% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 60% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 30/01/2024

Work in progress | 55% Completed

Work in progress

Kozhikode PH Dn EE
Date: 29/01/2024

Work in progress | 55% Completed

Work in progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 55% Completed

Work in progress

Kozhikode PH Dn EE
Date: 08/01/2024

Work in progress | 49% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 07/01/2024

Work in progress | 49% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 06/01/2024

Work in progress | 49% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 05/01/2024

Work in progress | 49% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 03/01/2024

Work in progress | 49% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 01/01/2024

Work in progress | 48% Completed

Work in Progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 48% Completed

Work in progress-Pipe laid-570m, FHTC-194, Tagged-84 nos. HTC-52

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 45% Completed

Work in progress

Kozhikode PH Dn EE
Date: 20/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 18/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 17/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 16/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 15/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 14/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 13/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 11/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 10/11/2023

Work in progress | 42% Completed

Work in progress. FHTC-172, HTC-34, Pipe laid-570m

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 42% Completed

work in progress

Kozhikode PH Dn EE
Date: 27/10/2023

Work in progress | 40% Completed

work in progress

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 35% Completed

work in progress

Kozhikode PH Dn EE
Date: 14/09/2023

Work in progress | 26% Completed

Pipe laying work in progress.

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 25% Completed

Pipe laying work in progress.

Kozhikode PH Dn EE
Date: 17/08/2023

Work in progress | 10% Completed

Pipe laying work in progress.

Kozhikode PH Dn EE
Date: 07/08/2023

Work in progress | 4% Completed

Pipe laying work in progress. HTC Provided-15 nos. Reinstating House Connections-8 nos.

Kozhikode PH Dn EE
Date: 24/07/2023

Work in progress | 3% Completed

Pipe laying work started

Kozhikode PH Dn EE
Date: 18/07/2023

Work in progress | 1% Completed

pIPE LAYING STARTED-110MM PVC-70M

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Pipe supplied

Kozhikode PH Dn EE
Date: 05/07/2023

Work has started | 0% Completed

Pipe supplied

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Pipe supplied

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Pipe supplied

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 07/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 05/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 25/05/2023

Work in progress | 1% Completed

Agreement Executed