CWSS TO MANNOORKARA,VEERANAKAVU AND PERUMKULAM VILLAGES PHASE-I
Project |
CWSS TO MANNOORKARA,VEERANAKAVU AND PERUMKULAM VILLAGES PHASE-I |
Project Code |
TVMGOI1013552 |
Type |
Main project |
Funding Agency |
GOI |
Category |
NRDWP-XVSLSSC |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Projects details are
1. Design , construction and commissioning of 9 meter dia well cum pump house at Aniyilakadavu
2. Supplying,Laying,Testing & Commissioning of 400 DI K9 Raw water pumping main from Well at Aniyilakadavu to WTP at Thozhuthinkarachira
3. Construction of 11.50 MLD WTP at Thozhuthinkarachira.
4. Supplying,Laying,Testing & Commissioning of (i)150mm DI K9 CWPM from Kallode Jn to Proposed OHSR at Aniyilakunnu. (ii)350mm DI K9 CWPM from WTP(sump)-Thozhuthinkarachira to Parambukada Jn (iii) 200mm DI K9 CWPM from Parambukada Jn to proposed OHSR at Panniyode (iv)250mm DI K9 CWPM from WTP to Kallode Jn.
5. Construction of 1.40 LL OHSR at Aniyilakunnu.
6. Construction of 3.50 LL OHSR at Panniyode.
7. Construction of Transformer Room at WTP site & Well Cum Pump House site.
8.Supply,Erection,Testing & Commissioning of (i) 500 KVA Indoor Transformer at WTP site,Thozhuthinkarachira. (ii)315 KVA Indoor Transformer at Well Cum Pump House site,Aniyilakadavu.
9.Supply,Erection,Testing & Commissioning of (i) Vertical Turbine Pump Set at Aniyilakadavu. (ii)Centrifugal pump Sets at WTP,Thozhuthinkarachira |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
207500000
|
AS Number |
WS/88/2013-14 |
TS Amount (Rs) |
204322000 |
TS Number |
KWA/CE(SR)/42/2013-14; TS/2018-2019/2018/14416; TS/2018-2019/2018/14737; TS/2018-2019/2018/15214 |
Total Bill Submitted (Rs) |
106252000 |
Total Bill Paid (Rs) |
103178000 |
Population Benefitted |
109963 |
Capacity in MLD |
11.50 |
Actual Project Completion Date |
29 Mar 2021 |
Coverage |
Design Population for the entire scheme in 2029 is 109963 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Phase I- Package I |
Trivandrum Project Dn |
|
2 |
Phase I- Package II |
Trivandrum Project Dn |
|
3 |
Phase I- Package III |
Trivandrum Project Dn |
|
4 |
Phase I- Package IV |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Feb 2024 |
Package I: (100% Completed) Package II: (97% Completed) Power allocation from KSEB (tendering stage-kattakada division )and 150mm DI flanged pipe for a length of 66m is pending due to public protest Package III: (100% Completed) Package IV: (100% completed) |
Thiruvananthapuram Project AE4 |
|
29 Mar 2023 |
Package I: (100% Completed)
Package II: (97% Completed)
Power allocation from KSEB and 150mm DI flanged pipe for a length of 66m is pending due to public protest
Package III: (100% Completed)
Package IV: (100% completed) |
Thiruvananthapuram Project AE4 |
|
19 May 2022 |
Package I: (100% Completed)
1. Design , construction and commissioning of 9 meter dia well cum pump house at Aniyilakadavu
2. Supplying,Laying,Testing & Commissioning of 400 DI K9 Raw water pumping main from Well at Aniyilakadavu to WTP at Thozhuthinkarachira
Package II: (79% Completed)
1. Pile for clarifloculator 1 and2 (78 No.): completed Pile for Filter house (67 No.) : completed Pile for Aerator+ Flash mixer+ Channel ( 17 No) :completed Pile for Transformer room(7 No.) : Completed
2. At WTP, civil work for first and second Clarifloculator completed
3. Civil work for filter house and flash mixer completed and plastering progressing.
4. Civil work for sump completed except brick work
5. Civil work for Transformer room at aniyilakadav completed except brick work
6.Work in progress:
1) Aerator central shaft,supporting beam concreted and column over supporting beam concrete is in progress.
2) Filter house outside plastering work is in progress.
3) Transformer room (at WTP) civil structure completed
4. Clear water channel concrete work us in progress
2. Supplying,Laying,Testing & Commissioning of
(i)150mm DI K9 CWPM : Total pipe laid for a length of 2090.30m (90% Completed)
(iI)250mm DI K9 CWPM : Completed
Package III: (95% Completed)
1.350mm DI K9 clear water pumping main from Parambukada Jn towards WTP is in progress and total pipe laid for a length of 1396.70m
2. 200mm DI K9 clear water pumping main from Panniyode OHSR site towards WTP is in progress and total pipe laid for a length of 2649.2m.
3. Construction of 3.50 LL OHSR at Panniyode completed.
Package IV: (55% completed)
The components of package IV consist of
1. Indoor Transformer of 500 KVA at WTP and 315 KVA at Well Cum Pump House site
2. Supply, Erection, Testing & Commissioning of Vertical Turbine Pump Set and Centrifugal pump Sets at WTP
Status of work:
1. Contractor supplied Vertical Turbine Pump Set ( 2 No.) and Centrifugal pump Sets (4 No.) at site. 2. Erection, Testing & Commissioning of the pumps can be started only after the partial completion of Package II, which consists of construction of Transformer rooms and Pump house at WTP |
Thiruvananthapuram Project AE4 |
|
01 Mar 2022 |
OVERALL STATUS: 1. Construction of 3.50 LL OHSR at Panniyode completed. 2. Supplying,Laying,Testing & Commissioning of (i)150mm DI K9 CWPM : Total pipe laid for a length of 2090.30m (90% Completed) (ii)350mm DI K9 CWPM : Completed (iii) 200mm DI K9 CWPM : Completed (iv)250mm DI K9 CWPM : Completed 3. Pile for clarifloculator 1 and2 (78 No.): completed Pile for Filter house (67 No.) : completed Pile for Aerator+ Flash mixer+ Channel ( 17 No) :completed Pile for Transformer room(7 No.) : Completed 4. At WTP, civil work for first and second Clarifloculator completed 5. Civil work for filter house and flash mixer completed and plastering progressing. 6. Construction of sump is in progress |
Thiruvananthapuram Project AE4 |
|
13 Feb 2022 |
OVERALL STATUS: 1. Construction of 3.50 LL OHSR at Panniyode completed. 2. Supplying,Laying,Testing & Commissioning of (i)150mm DI K9 CWPM : Total pipe laid for a length of 2090.30m (90% Completed) (ii)350mm DI K9 CWPM : Completed (iii) 200mm DI K9 CWPM : Completed (iv)250mm DI K9 CWPM : Completed 3. Pile for clarifloculator 1 and2 (78 No.): completed Pile for Filter house (67 No.) : completed Pile for Aerator+ Flash mixer+ Channel ( 17 No) :completed Pile for Transformer room(7 No.) : Completed 4. At WTP, civil work for first and second Clarifloculator completed 5. Civil work for filter house and flash mixer completed and plastering progressing. 6. Construction of sump started and is in progress |
Thiruvananthapuram Project AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/02/2014 |
Scheduled date of Completion of the Project |
30 Jul 2022 |
Expected date of Completion |
31/01/2023 |
Processing Dates
AS Date |
30 Oct 2013 |
TS Date |
26 Feb 2019 |