Phase I- Package I

Project Phase I- Package I
Project Code TVMGOI1013552P1
Type Package
Main Project CWSS TO MANNOORKARA,VEERANAKAVU AND PERUMKULAM VILLAGES PHASE-I
Funding Agency GOI
Category NRDWP-XVSLSSC
Type of scheme Water Supply
Scheme
Description Subjected work consists of 4 packages, in which component wise details of package I is as follows 1. Design , construction and commissioning of 9 meter dia well cum pump house at Aniyilakadavu 2. Supplying,Laying,Testing & Commissioning of 400 DI K9 Raw water pumping main from Well at Aniyilakadavu to WTP at Thozhuthinkarachira
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 207500000
TS Number KWA/CE(SR)/42/2013-14
Technical specification Subjected work consists of 4 packages, in which component wise details of package I is as follows 1. Design , construction and commissioning of 9 meter dia well cum pump house at Aniyilakadavu 2. Supplying,Laying,Testing & Commissioning of 400 DI K9 Raw water pumping main from Well at Aniyilakadavu to WTP at Thozhuthinkarachira

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/02/2014
Scheduled date of Completion as per agreement 31 Aug 2016
Expected date of Completion 31/08/2016

Processing Dates

TS Date 17 Dec 2013
Estimate Approval 17 Dec 2013
NIT Approval 20 Jan 2015
Tender Closing 15 Apr 2015
Technichal Pre-Qualification 16 Jun 2015
Price bid opening 21 Jul 2015

Approval Dates

Workorder Date 01 Sep 2015
NA 07 Sep 2015

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE4
Date: 03/02/2022

Work has been completed | 100% Completed

Work Completed.

Thiruvananthapuram Project AE4
Date: 02/02/2022

Work has been completed | 100% Completed

Work Completed.