Project | Phase I- Package III |
---|---|
Project Code | TVMGOI1013552P3 |
Type | Package |
Main Project | CWSS TO MANNOORKARA,VEERANAKAVU AND PERUMKULAM VILLAGES PHASE-I |
Funding Agency | GOI |
Category | NRDWP-XVSLSSC |
Type of scheme | Water Supply |
Scheme | |
Description | Subjected work consists of 4 packages, in which component wise details of package III is as follows. 1. Supplying,Laying,Testing and Commissioning of 350mm DI K9 CWPM from WTP(sump)-Thozhuthinkarachira to Parambukada Jn 2.Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM from Parambukada Jn to proposed OHSR at Panniyode 3. Construction of 3.50 LL OHSR at Panniyode. |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 42800000 |
TS Number | TS/2018-2019/2018/14737 |
Technical specification | Estimate is based on 2016 DSR Subjected work consists of 4 packages, in which component wise details of package III is as follows. 1. Supplying,Laying,Testing and Commissioning of 350mm DI K9 CWPM from WTP(sump)-Thozhuthinkarachira to Parambukada Jn 2.Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM from Parambukada Jn to proposed OHSR at Panniyode 3. Construction of 3.50 LL OHSR at Panniyode. |
Contractor | EDWIN PRASAD S (Mob: 9447217039) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Jul 2022 |
Expected date of Completion | 30/07/2022 |
TS Date | 26 Feb 2019 |
---|---|
Estimate Approval | 26 Feb 2019 |
NIT Approval | 08 Apr 2019 |
Tender Closing | 23 May 2019 |
Technichal Pre-Qualification | 30 Jul 2019 |
Price bid opening | 02 Aug 2019 |
Workorder Date | 30 Sep 2019 |
---|---|
NA | 23 Oct 2019 |
Thiruvananthapuram Project AE4 |
Date: 01/04/2023 |
Work has been completed | 100% Completed
Interconnection works done.
Thiruvananthapuram Project AE4 |
Date: 31/03/2023 |
Work in progress | 97% Completed
Only Interconnection works left, that can be only execute after completed of package 2 (construction of WTP).