Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Phase I- Package III

Project Phase I- Package III
Project Code TVMGOI1013552P3
Type Package
Main Project CWSS TO MANNOORKARA,VEERANAKAVU AND PERUMKULAM VILLAGES PHASE-I
Funding Agency GOI
Category NRDWP-XVSLSSC
Type of scheme Water Supply
Scheme
Description Subjected work consists of 4 packages, in which component wise details of package III is as follows. 1. Supplying,Laying,Testing and Commissioning of 350mm DI K9 CWPM from WTP(sump)-Thozhuthinkarachira to Parambukada Jn 2.Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM from Parambukada Jn to proposed OHSR at Panniyode 3. Construction of 3.50 LL OHSR at Panniyode.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 42800000
TS Number TS/2018-2019/2018/14737
Technical specification Estimate is based on 2016 DSR Subjected work consists of 4 packages, in which component wise details of package III is as follows. 1. Supplying,Laying,Testing and Commissioning of 350mm DI K9 CWPM from WTP(sump)-Thozhuthinkarachira to Parambukada Jn 2.Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM from Parambukada Jn to proposed OHSR at Panniyode 3. Construction of 3.50 LL OHSR at Panniyode.
Contractor EDWIN PRASAD S (Mob: 9447217039)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/03/2020
Scheduled date of Completion as per agreement 30 Jul 2022
Expected date of Completion 30/07/2022

Processing Dates

TS Date 26 Feb 2019
Estimate Approval 26 Feb 2019
NIT Approval 08 Apr 2019
Tender Closing 23 May 2019
Technichal Pre-Qualification 30 Jul 2019
Price bid opening 02 Aug 2019

Approval Dates

Workorder Date 30 Sep 2019
NA 23 Oct 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE4
Date: 01/04/2023

Work has been completed | 100% Completed

Interconnection works done.

Thiruvananthapuram Project AE4
Date: 31/03/2023

Work in progress | 97% Completed

Only Interconnection works left, that can be only execute after completed of package 2 (construction of WTP).