Project | Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
---|---|
Project Code | TCRJJM08205242P1 |
Type | Package |
Main Project | Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing 4400 FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 138660000 |
TS Number | TS/2020-2021/2020/21871 CE KOCHI dtd 22/10/2020 |
Technical specification | 4400 nos of FHTCs |
Contractor | Mr.M.Ashraf (Mob: 9447535653) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Jun 2022 | Pending | Pending | Road Cut Related Risk | Application submitted to NH section for road cutting request. due to corrections they returned the application with adequate directions. | No comments available. | Pending |
10 Jun 2022 | Pending | Pending | Road Cut Related Risk | Application submitted to NH section for road cutting request. due to corrections they returned the application with adequate directions | No comments available. | Pending |
27 Feb 2021 | Pending | Pending | Road Cut Related Risk | 1) ROW/104860/7269 - Edamuttam to Kurisupally 2) ROW/104860/7271 - Edamuttam Jn. crossing 3) ROW/104860/7272 - Kothakulam Jn. crossing | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2022 |
Expected date of Completion | 30/06/2023 |
TS Date | 22 Oct 2020 |
---|---|
Estimate Approval | 22 Oct 2020 |
NIT Approval | 25 Nov 2020 |
Tender Closing | 04 Nov 2020 |
Technichal Pre-Qualification | 04 Nov 2020 |
Price bid opening | 04 Nov 2020 |
Workorder Date | 30 Dec 2020 |
---|---|
NA | 29 Jan 2021 |
Vadanappilly AE |
Date: 24/06/2024 |
Work in progress | 50% Completed
14th and Final Bill submitted. Work Short closed.
Vadanappilly AE |
Date: 12/06/2024 |
Work in progress | 50% Completed
1559 connections completed out of 4400 (FHTC -1477 and 82htc),14th and final bill submitted..