- Home
- Jal Jeevan Mission (JJM)-Balance Works a...
Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Project |
Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work |
Project Code |
PKDJJM122015877 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
717000000
|
AS Number |
GO(Rt) no.777/2020/WRD/TVM/DTD 24.12.2020 |
TS Amount (Rs) |
9902828 |
TS Number |
TS/WRD/KWA/CE/NR/EST/TS/28149/2023 DTD 11.1.2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
28751 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
31 Jul 2024 |
Coverage |
KOZHINJAMPARA GRAMAPANCHAYATH |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Jun 2024 |
Work in progress | 50% Completed | 20/06/2024
Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M |
Chittur Project Dn - AE 4 |
|
12 Jun 2024 |
Work in progress | 37% Completed | 12/06/2024
Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M |
Chittur Project Dn - AE 4 |
|
06 Jun 2024 |
Work in progress | 37% Completed | 06/06/2024
Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M |
Chittur Project Dn - AE 4 |
|
01 Jun 2024 |
Work in progress | 37% Completed | 01/06/2024
Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3529m 2). 80mm GI pipe = 246M |
Chittur Project Dn - AE 4 |
|
23 May 2024 |
Work in progress | 37% Completed | 23/05/2024
Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3333m 2). 80mm GI pipe = 246M |
Chittur Project Dn - AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2024 |
Scheduled date of Completion of the Project |
21 Jun 2024 |
Expected date of Completion |
31/08/2024 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
11 Jan 2024 |