Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work

Project Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Project Code PKDJJM122015877
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 717000000
AS Number GO(Rt) no.777/2020/WRD/TVM/DTD 24.12.2020
TS Amount (Rs) 9902828
TS Number TS/WRD/KWA/CE/NR/EST/TS/28149/2023 DTD 11.1.2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 28751
Capacity in MLD 8.00
Actual Project Completion Date 31 Jul 2024
Coverage KOZHINJAMPARA GRAMAPANCHAYATH

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 50% Completed | 20/06/2024 Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M Chittur Project Dn - AE 4
12 Jun 2024 Work in progress | 37% Completed | 12/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
06 Jun 2024 Work in progress | 37% Completed | 06/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
01 Jun 2024 Work in progress | 37% Completed | 01/06/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3529m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
23 May 2024 Work in progress | 37% Completed | 23/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3333m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/02/2024
Scheduled date of Completion of the Project 21 Jun 2024
Expected date of Completion 31/08/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 11 Jan 2024