Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work

Project Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Project Code PKDJJM122015877P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Balance Works at Kozhinjampara and Adj.Panchayaths -Pipe line work-pipeline work
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 9902828
TS Number TS/WRD/KWA/CE/NR/EST/TS/28149/2023 DTD 11.1.2024
Technical specification DISTRIBUTION NET WORK AND PROVIDING FHTCS

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/02/2024
Scheduled date of Completion as per agreement 21 Jun 2024
Expected date of Completion 31/07/2024

Processing Dates

TS Date 11 Jan 2024
Estimate Approval 11 Jan 2024
NIT Approval 22 Feb 2024
Tender Closing 19 Jan 2024
Technichal Pre-Qualification 12 Jan 2024
Price bid opening 20 Jan 2024

Approval Dates

Workorder Date 14 Feb 2024
NA 22 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 4
Date: 27/06/2024

Work in progress | 52% Completed

Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M.

Chittur Project Dn - AE 4
Date: 20/06/2024

Work in progress | 50% Completed

Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M .