Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2024 Work in progress | 52% Completed | 27/06/2024 Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M Chittur Project Dn - AE 4
20 Jun 2024 Work in progress | 50% Completed | 20/06/2024 Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M Chittur Project Dn - AE 4
12 Jun 2024 Work in progress | 37% Completed | 12/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
06 Jun 2024 Work in progress | 37% Completed | 06/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
01 Jun 2024 Work in progress | 37% Completed | 01/06/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3529m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
23 May 2024 Work in progress | 37% Completed | 23/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3333m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
16 May 2024 Work in progress | 37% Completed | 16/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3057m 2). 80mm GI pipe = 246M Chittur Project Dn - AE 4
09 May 2024 Work in progress | 37% Completed | 09/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 2980m 2). 80mm GI pipe = 246 Chittur Project Dn - AE 4
22 Apr 2024 Work in progress | 30% Completed | 22/04/2024 Total- 2.626km laid / OUT OF 8.5 KM 1.90MM PVC 6 Kg = 2560m 2. 80mm GI pipe = 66M Chittur Project Dn - AE 4
15 Apr 2024 Work in progress | 25% Completed | 15/04/2024 Total- 2.14km laid / OUT OF 8.5 KM 1.90MM PVC 6 Kg = 2140m Chittur Project Dn - AE 4