Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2024 | Work in progress | 52% Completed | 27/06/2024 Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M | Chittur Project Dn - AE 4 | |
20 Jun 2024 | Work in progress | 50% Completed | 20/06/2024 Total- 5.475 km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 5067 M 2). 80MM GI pipe = 408 M | Chittur Project Dn - AE 4 | |
12 Jun 2024 | Work in progress | 37% Completed | 12/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M | Chittur Project Dn - AE 4 | |
06 Jun 2024 | Work in progress | 37% Completed | 06/06/2024 Total- 3.426km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3729.5m 2). 80mm GI pipe = 246M | Chittur Project Dn - AE 4 | |
01 Jun 2024 | Work in progress | 37% Completed | 01/06/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3529m 2). 80mm GI pipe = 246M | Chittur Project Dn - AE 4 | |
23 May 2024 | Work in progress | 37% Completed | 23/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3333m 2). 80mm GI pipe = 246M | Chittur Project Dn - AE 4 | |
16 May 2024 | Work in progress | 37% Completed | 16/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 3057m 2). 80mm GI pipe = 246M | Chittur Project Dn - AE 4 | |
09 May 2024 | Work in progress | 37% Completed | 09/05/2024 Total- 3.226km laid / OUT OF 8.5 KM 1).90MM PVC 6 Kg = 2980m 2). 80mm GI pipe = 246 | Chittur Project Dn - AE 4 | |
22 Apr 2024 | Work in progress | 30% Completed | 22/04/2024 Total- 2.626km laid / OUT OF 8.5 KM 1.90MM PVC 6 Kg = 2560m 2. 80mm GI pipe = 66M | Chittur Project Dn - AE 4 | |
15 Apr 2024 | Work in progress | 25% Completed | 15/04/2024 Total- 2.14km laid / OUT OF 8.5 KM 1.90MM PVC 6 Kg = 2140m | Chittur Project Dn - AE 4 |