: Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area

Project : Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area
Project Code KLMDEPO072212396P1
Type Package
Main Project : Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description : Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana -Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North ofArackalil Jn to IRE Mining Area
Status On-going
District Kollam
Executing Office Chavara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 662000
TS Number 9746/2022-2023
Technical specification Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North ofArackalil Jn to IRE Mining Area

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/12/2022
Scheduled date of Completion as per agreement 13 Feb 2023
Expected date of Completion 13/02/2023

Processing Dates

TS Date 12 Jul 2022
Estimate Approval 12 Jul 2022
NIT Approval 12 Jul 2022
Tender Closing 27 Sep 2022
Technichal Pre-Qualification 09 Nov 2022
Price bid opening 30 Sep 2022

Approval Dates

Workorder Date 14 Nov 2022
NA 14 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavara AE
Date: 19/07/2023

Work has been completed | 100% Completed

Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill submitted..

Chavara AE
Date: 14/07/2023

Work in progress | 98% Completed

Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill under preparation..