Chavara AE
Date: 19/07/2023

Work has been completed | 100% Completed

Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill submitted.

Chavara AE
Date: 14/07/2023

Work in progress | 98% Completed

Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill under preparation.

Chavara AE
Date: 11/07/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 07/07/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 04/07/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 30/06/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 27/06/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 23/06/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 20/06/2023

Work in progress | 90% Completed

Agreement executed On 14.12.2022, Material supply order issued, work in progress

Chavara AE
Date: 16/06/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 13/06/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 09/06/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 06/06/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 02/06/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 31/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 26/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 23/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 19/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 15/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 11/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 08/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 04/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 01/05/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 27/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 24/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AEE
Date: 17/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 13/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 10/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 04/04/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 31/03/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 28/03/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 24/03/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 21/03/2023

Work in progress | 5% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 18/03/2023

Work in progress | 4% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 14/03/2023

Work in progress | 4% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 10/03/2023

Work in progress | 4% Completed

interim order extended

Chavara AE
Date: 07/03/2023

Work in progress | 4% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 04/03/2023

Work in progress | 4% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 02/03/2023

Work in progress | 3% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 27/02/2023

Work in progress | 3% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 24/02/2023

Work in progress | 3% Completed

Agreement executed On 14.12.2022, Material supply order issued, work started

Chavara AE
Date: 21/02/2023

Work in progress | 2% Completed

Agreement executed On 14.12.2022, Material supply order issued

Chavara AE
Date: 17/02/2023

Work in progress | 1% Completed

Agreement executed On 14.12.2022, Material supply order issued

Chavara AE
Date: 14/02/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 10/02/2023

Work has started | 2% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 08/02/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 06/02/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 02/02/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 30/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 27/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 24/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 21/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 19/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 16/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 13/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 10/01/2023

Work has started | 0% Completed

Agreement executed On 14.12.2022, work not yet started

Chavara AE
Date: 07/01/2023

Work in progress | 2% Completed

Agreement executed On 14.12.2022

Chavara AE
Date: 03/01/2023

Work in progress | 2% Completed

Agreement executed On 14.12.2022

Chavara AE
Date: 28/12/2022

Work in progress | 2% Completed

Agreement executed On 14.12.2022,work not yet started

Chavara AE
Date: 26/12/2022

Work in progress | 2% Completed

pipe laying work completed, interconnection work ongoing

Chavara AE
Date: 23/12/2022

Work in progress | 2% Completed

Agreement executed On 14.12.2022

Chavara AE
Date: 20/12/2022

Work in progress | 2% Completed

Agreement executed On 14.12.2022

Chavara AE
Date: 16/12/2022

Work in progress | 2% Completed

Agreement executed On 14.12.2022

Chavara AE
Date: 12/12/2022

Work in progress | 1% Completed

Offer Received and Selection Notice Issued and agreement not executed

Chavara AE
Date: 06/12/2022

Work in progress | 1% Completed

Offer Received and Selection Notice Issued

Chavara AE
Date: 03/12/2022

Work in progress | 1% Completed

Offer Received and Selection Notice Issued

Chavara AE
Date: 29/11/2022

Work has started | 0% Completed

Offer Received and Selection Notice Issued

Chavara AE
Date: 25/11/2022

Work in progress | 1% Completed

Offer Received and Selection Notice Issued

Chavara AE
Date: 24/11/2022

Work has started | 0% Completed

Single offer recieved at PH Division Kollam were sanctioned vide proceedings No: DB2/3014/DW/IRE//PHDNK/2022 Dated: 09.11.2022 and submitted to Sub Div for further action

Kollam PH Dn EE
Date: 22/11/2022

Work in progress | 0% Completed

Single offer recieved at PH Division Kollam were sanctioned vide proceedings No: DB2/3014/DW/IRE//PHDNK/2022 Dated: 09.11.2022 and submitted to Sub Div for further action

Chavara AE
Date: 21/11/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 15/11/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 11/11/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 07/11/2022

Work in progress | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Kollam PH Dn EE
Date: 02/11/2022

Work in progress | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 31/10/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 27/10/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 25/10/2022

Work has started | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AE
Date: 18/10/2022

Work in progress | 0% Completed

Retender opened on 30.09.22. Single offer received submitted to division.

Chavara AEE
Date: 15/10/2022

Work has started | 0% Completed

Retender opened on 27.09.22. Single offer received submitted to division for sanction on 13.10.22

Chavara AEE
Date: 14/10/2022

Work has started | 0% Completed

Retender opened on 29.07.22. Single offer received. submitted to division for sanction