: Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area
| Project |
: Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area |
| Project Code |
KLMDEPO072212396 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
: Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana -Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North ofArackalil Jn to IRE Mining Area |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Chavara PH Sub Dn |
| AS Amount (Rs) |
673000
|
| AS Number |
6361/2121 |
| TS Amount (Rs) |
662000 |
| TS Number |
9746/2022-2023 |
| Total Bill Submitted (Rs) |
1 |
| Total Bill Paid (Rs) |
1 |
| Population Benefitted |
100 |
| Capacity in MLD |
0.01 |
| Actual Project Completion Date |
05 Jul 2023 |
| Coverage |
IRE mining area |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
: Deposit Work - Chavara Grama Panchayat - CWSS to Chavara & Panmana - Supplying, Laying and Interconnecting 110 mm HDPE line through TS canal from North of Arackalil Jn to IRE Mining Area |
Chavara PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 26 Aug 2023 |
Work completed on 05.072023 |
Chavara AE |
|
| 19 Jul 2023 |
Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill submitted. |
Chavara AE |
|
| 14 Jul 2023 |
Agreement executed On 14.12.2022, Material supply order issued, work completed. Bill under preparation. |
Chavara AE |
|
| 11 Jul 2023 |
Agreement executed On 14.12.2022, Material supply order issued, work in progress |
Chavara AE |
|
| 07 Jul 2023 |
Agreement executed On 14.12.2022, Material supply order issued, work in progress |
Chavara AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
14/12/2022 |
| Scheduled date of Completion of the Project |
13 Feb 2023 |
| Expected date of Completion |
13/02/2023 |
Processing Dates
| AS Date |
05 May 2022 |
| TS Date |
12 Jul 2022 |