Project | KIIFB-RWSS to Vechoochira- Relaying of damaged pipe lines Chethackal- Koothattukulam and Treatment plant to Vechoochira town. |
---|---|
Project Code | PTAKIIFB0418887P1 |
Type | Package |
Main Project | KIIFB-RWSS to Vechoochira- Relaying of damaged pipe lines Chethackal- Koothattukulam and Treatment plant to Vechoochira town. |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB-RWSS to Vechoochira- Relaying of damaged pipe lines Chethackal- Koothattukulam and Treatment plant to Vechoochira town. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Ranni Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 47320000 |
TS Number | TS/2019-2020/2018/8511 |
Technical specification | Replacing Damaged Pumping main from Navodaya Jn. to Koothattukulam Jn (150mm DI K9 pipe - 5500m) and Providing and laying Distribution line from Vaka Mukk to Pullikkallu booster PH (110mm PVC 3000m & 90mm PVC 1000m & Provisions for GI Pipes) |
Contractor | M/S Minartech Developers Pvt. Ltd (Mob: 9446683721) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
14 Jul 2021 | Pending | Pending | Road Cut Related Risk | Remitting TSD/BG demanded by PWD for Rs 41,95,563/- | No comments available. | Pending |
27 Nov 2020 | Pending | Pending | Contract Related Risks | Reinstating water supply in 4 wards of Vechoochira Panchayath is getting delayed because of the slow progress. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/09/2020 |
---|---|
Scheduled date of Completion as per agreement | 22 Jan 2021 |
Expected date of Completion | 31/12/2022 |
TS Date | 28 Jan 2020 |
---|---|
Estimate Approval | 28 Jan 2020 |
NIT Approval | 28 Jan 2020 |
Tender Closing | 26 Feb 2020 |
Price bid opening | 28 Feb 2020 |
Workorder Date | 26 May 2020 |
---|---|
NA | 23 Sep 2020 |
Ranni PH Sn - AE |
Date: 02/05/2024 |
Work in progress | 40% Completed
Work Terminated on 30/12/2022 as per Order No. SE/PHC/TVLA/3266/2018, dated:30/12/2022.
Ranni PH Sn - AE |
Date: 29/04/2024 |
Work in progress | 40% Completed
Work Terminated on 30/12/2022 as per Order No. SE/PHC/TVLA/3266/2018, dated:30/12/2022.