Work Termination- Proceedings of The Superintending Engineer
Proceedings of The Superintending Engineer
termination letter
Time extension application
Reminding Letter
PWD DLP Road BG/TSD remittance letter
SD for Rs 41,95,563/- to be remitted to PWD
Delay reporting
The explanation for non supply of DI pipes at site furnished by the Contractor is found to be not satisfactory. Hence the matter reported to higher office for further actions.
Notice no-2 issued to Contractor
Notice issued on 26/08/21 to the Contractor for completing the work with in the extended completion period which expires on 31/12/2021. Explanation also sought for not supplying DI pipes.
PWD - BG Letter
PWD demanded Rs 55,56,205/- as BG/TSD and Rs 3,37,682/- as Supervision charges for cutting permission in DLP road.
Abstract of TS Estimate
Abstract of TS Estimate