Work Termination- Proceedings of The Superintending Engineer

16/03/2023 | File: termination Order.pdf | Download

Proceedings of The Superintending Engineer

termination letter

30/06/2022 | File: New doc Jun 28, 2022 11.26 AM (1).pdf | Download

Time extension application

31/05/2022 | File: New doc May 31, 2022 1.20 PM.pdf | Download

Reminding Letter

13/02/2022 | File: | Download

PWD DLP Road BG/TSD remittance letter

04/02/2022 | File: | Download

SD for Rs 41,95,563/- to be remitted to PWD

Schedule

03/02/2022 | File: | Download

Schedule

Delay reporting

25/09/2021 | File: Minartech Delay Reporting.pdf | Download

The explanation for non supply of DI pipes at site furnished by the Contractor is found to be not satisfactory. Hence the matter reported to higher office for further actions.

Notice no-2 issued to Contractor

25/09/2021 | File: Notice to Minartech 26-08-21.pdf | Download

Notice issued on 26/08/21 to the Contractor for completing the work with in the extended completion period which expires on 31/12/2021. Explanation also sought for not supplying DI pipes.

PWD - BG Letter

25/09/2021 | File: PWD BG-TSD letter.pdf | Download

PWD demanded Rs 55,56,205/- as BG/TSD and Rs 3,37,682/- as Supervision charges for cutting permission in DLP road.

Abstract of TS Estimate

27/03/2021 | File: 8887 Abstract of Estimate.pdf | Download

Abstract of TS Estimate

TS Slip

27/03/2021 | File: 8887 TS_SLIP.pdf | Download

TS Slip

Administrative Sanction

29/01/2021 | File: KIIFB AS.pdf | Download

Administrative Sanction