Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission - CWSS to Mavelikkara and adjoining Panchayaths-Supplying and Laying of Distribution Network and giving FHTC for Chettikulangara Panchayath

Project Jal Jeevan Mission - CWSS to Mavelikkara and adjoining Panchayaths-Supplying and Laying of Distribution Network and giving FHTC for Chettikulangara Panchayath
Project Code ALPJJM052211954
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - CWSS to Mavelikkara and adjoining Panchayaths-Supplying and Laying of Distribution Network and giving FHTC for Chettikulangara Panchayath
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
AS Amount (Rs) 1599030000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 945350000
TS Number WRD/KWA-CE(CR)/EST_TS/4207/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 47500
Capacity in MLD 30.00
Actual Project Completion Date Date is not specified
Coverage Chettikulagara and Thazhakkara panchayat

Packages

No. Project Name Location View
1 JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats Alappuzha Project Dn
2 JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to Thazhakkara panchayat Alappuzha Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 May 2024 Out of 12040 FHTCs, around 2670 FHTCs and 525 HTCs done, 90 mm PVC laying around 95.091 km laying done,110 mm PVC laid out of 5592 meter PVC pipe to be laid 2724 meter laying has been completed, 160 mm PVC laid out of 27.611 km PVC pipe to be laid 7459 meter laying has been completed.250 mm DI pipe to be laid 698 m 2)Excavation started for laying 90mm pvc ,Kallumala, Thazhakkara panchayath( Work started on 10.05.2024) Alappuzha Project Dn PM
08 May 2024 Out of 12040 FHTCs, around 2670 FHTCs and 525 HTCs done, 90 mm PVC laying around 95.091 km laying done,110 mm PVC laid out of 5592 meter PVC pipe to be laid 2724 meter laying has been completed, 160 mm PVC laid out of 27.611 km PVC pipe to be laid 7459 meter laying has been completed.250 mm DI pipe to be laid 698 m Alappuzha Project Dn PM
22 Apr 2024 Out of 12040 FHTCs, around 2645 FHTCs and 443 HTCs done, 90 mm PVC laying around 90.136 km laying done,110 mm PVC laid out of 5592 meter PVC pipe to be laid 1572 meter laying has been completed, 160 mm PVC laid out of 27.611 km PVC pipe to be laid 4300 meter laying has been completed.250 mm DI pipe to be laid 698 m Alappuzha Project Dn PM
06 Apr 2024 Out of 12040 FHTCs, around 2645 FHTCs and 443 HTCs done, 90 mm PVC laying around 90.136 km laying done,110 mm PVC laid out of 5592 meter PVC pipe to be laid 1572 meter laying has been completed, 160 mm PVC laid out of 27.611 km PVC pipe to be laid 4300 meter laying has been completed.250 mm DI pipe to be laid 698 m Alappuzha Project Dn PM
20 Mar 2024 Out of 12040 FHTCs, around 2645 FHTCs and 443 HTCs done, 90 mm PVC laying around 90.136 km laying done,110 mm PVC laid out of 5592 meter PVC pipe to be laid 1572 meter laying has been completed, 160 mm PVC laid out of 27.611 km PVC pipe to be laid 4300 meter laying has been completed.250 mm DI pipe to be laid 698 m ,Work order issued on 25.05.2023 Alappuzha Project Dn PM

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/05/2023
Scheduled date of Completion of the Project 05 Apr 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 13 May 2022
TS Date 20 Oct 2022

Other details

Project Officers View