JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats

Project JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats
Project Code ALPJJM052211954P1
Type Package
Main Project Jal Jeevan Mission - CWSS to Mavelikkara and adjoining Panchayaths-Supplying and Laying of Distribution Network and giving FHTC for Chettikulangara Panchayath
Funding Agency JJM
Category JJM - Automation
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats.
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 526520000
TS Number WRD/KWA-CE(CR)/EST_TS/3909/2022_26_1_1
Technical specification The project envisaged for enhancing the drinking water supply rate to 150 lpcd to the inhabitants of the Mavelikkara Municipal area, and 100 lpcd to the occupants of Thazhakkara and Chettikulangara Panchayath. Thus, the ultimate water demand of the new water supply project for the year 2049 AD comes to 30 MLD. is the only feasible source to this Scheme. A new RCC well cum pump house 12m diameter in Achenkovil River near to the existing well is considered for the new proposal. This DER comprises of construction of 5LL OHSR at Karippuzha and 6LL OHSR at Chettikulangara, laying of transmission main, laying of new distribution lines and alteration of existing connections to new distribution lines and providing FHTC to remaining House Holds.
Contractor Praveenkumar.V (Mob: 9846969824)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/04/2023
Scheduled date of Completion as per agreement 19 Mar 2024
Expected date of Completion 31/05/2025

Processing Dates

TS Date 18 Oct 2022
Estimate Approval 18 Oct 2022
NIT Approval 19 Dec 2023
Technichal Pre-Qualification 27 Jan 2023
Price bid opening 28 Jan 2023

Approval Dates

Workorder Date 21 Feb 2023
NA 20 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Proj Dn AE 2
Date: 10/03/2025

Work in progress | 60% Completed

Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed. .

Alappuzha Proj Dn AE 2
Date: 09/03/2025

Work in progress | 60% Completed

Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed. .