Project | JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats |
---|---|
Project Code | ALPJJM052211954P1 |
Type | Package |
Main Project | Jal Jeevan Mission - CWSS to Mavelikkara and adjoining Panchayaths-Supplying and Laying of Distribution Network and giving FHTC for Chettikulangara Panchayath |
Funding Agency | JJM |
Category | JJM - Automation |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | JJM CWSS to Mavelikkara and adjoining panchayat providing FHTCS to chettikulagara panchayats. |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 526520000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/3909/2022_26_1_1 |
Technical specification | The project envisaged for enhancing the drinking water supply rate to 150 lpcd to the inhabitants of the Mavelikkara Municipal area, and 100 lpcd to the occupants of Thazhakkara and Chettikulangara Panchayath. Thus, the ultimate water demand of the new water supply project for the year 2049 AD comes to 30 MLD. is the only feasible source to this Scheme. A new RCC well cum pump house 12m diameter in Achenkovil River near to the existing well is considered for the new proposal. This DER comprises of construction of 5LL OHSR at Karippuzha and 6LL OHSR at Chettikulangara, laying of transmission main, laying of new distribution lines and alteration of existing connections to new distribution lines and providing FHTC to remaining House Holds. |
Contractor | Praveenkumar.V (Mob: 9846969824) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/04/2023 |
---|---|
Scheduled date of Completion as per agreement | 19 Mar 2024 |
Expected date of Completion | 31/05/2025 |
TS Date | 18 Oct 2022 |
---|---|
Estimate Approval | 18 Oct 2022 |
NIT Approval | 19 Dec 2023 |
Technichal Pre-Qualification | 27 Jan 2023 |
Price bid opening | 28 Jan 2023 |
Workorder Date | 21 Feb 2023 |
---|---|
NA | 20 Mar 2023 |
Alappuzha Proj Dn AE 2 |
Date: 10/03/2025 |
Work in progress | 60% Completed
Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed. .
Alappuzha Proj Dn AE 2 |
Date: 09/03/2025 |
Work in progress | 60% Completed
Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed Out of 12040 FHTCs, around 2741 FHTCs ,1517 HTC done. Out of 171486 m 90 mm PVC Pipe to be laid, 116949 m Laying has been completed. Out of 5592m 110 mm PVC Pipe to be laid, 3180 meter Laying has been completed. Out of 27611m 160 mm PVC Pipe to be laid, 10546 meter Laying has been completed. Out of 4992 m 250mm DI Pipe to be laid, 700 meter Laying has been completed. .