Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kollam Project HD
Date: 19/10/2020

Work has been completed | 100% Completed

work completed

Kollam Project HD
Date: 01/09/2020

Work in progress | 92% Completed

Structure completed. Plastering work progressing

Attached images

img

Kollam Project HD
Date: 15/08/2020

Work in progress | 90% Completed

Roof slab concreting completed. Plastering work Progressing

Kollam Project HD
Date: 30/07/2020

Work in progress | 82% Completed

plastering work progressing. side wall completed. roof slab shuttering work started

Kollam Project HD
Date: 10/07/2020

Work in progress | 80% Completed

internal column works & side wall works progressing

Kollam Project HD
Date: 26/06/2020

Work in progress | 79% Completed

Floor beam floor slab including haunches Completed on 25/06/2020

Attached images

img img

Kollam Project HD
Date: 18/06/2020

Work in progress | 57% Completed

Agreement executed. Design approved by CE(WASCON) and 49 Nos. piles , pile caps & plinth beam and column and beam upto bottom of floorslabcompleted .Work in progress .Time of completion expired on 21.1.20.Request submitted by the contractor to extent the time of completion upto 23.7.20