Kollam Project HD |
Date: 19/10/2020 |
Work has been completed | 100% Completed
work completed
Kollam Project HD |
Date: 01/09/2020 |
Kollam Project HD |
Date: 15/08/2020 |
Work in progress | 90% Completed
Roof slab concreting completed. Plastering work Progressing
Kollam Project HD |
Date: 30/07/2020 |
Work in progress | 82% Completed
plastering work progressing. side wall completed. roof slab shuttering work started
Kollam Project HD |
Date: 10/07/2020 |
Work in progress | 80% Completed
internal column works & side wall works progressing
Kollam Project HD |
Date: 26/06/2020 |
Kollam Project HD |
Date: 18/06/2020 |
Work in progress | 57% Completed
Agreement executed. Design approved by CE(WASCON) and 49 Nos. piles , pile caps & plinth beam and column and beam upto bottom of floorslabcompleted .Work in progress .Time of completion expired on 21.1.20.Request submitted by the contractor to extent the time of completion upto 23.7.20