Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work
Project |
Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work |
Project Code |
PKDJJM09219406P2 |
Type |
Package |
Main Project |
JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work |
Status |
On-going |
District |
Palakkad |
Executing Office |
Cherplassery PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
9870000 |
TS Number |
TS/16975/2022_26_1_1 |
Technical specification |
JJM 2020-2021 Supplying, laying, testing,
commissioning and maintenance of distribution
system providing FHTCs (1678 Nos) and
supply and erection of electromagnetic flow
meter in Vellinezhy panchayath-Phase II" is
awarded and execution is going on.To complete
the house connection awarded in this work it is
required to provide additional dstribution
network.Hence thisadditional work for street
main extention is arranged which include
laying of (75mm PVC 8 kg pipe-1320m, 63mm
PVC 8 kg pipe-9900m,50mm GI pipe-
1152m,65mm GI pipe -300m) and concrete of
LSGD road. |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
24/02/2023 |
Scheduled date of Completion as per agreement |
05 Apr 2023 |
Expected date of Completion |
20/12/2023 |
Processing Dates
TS Date |
12 Jan 2023 |
Estimate Approval |
12 Jan 2023 |
NIT Approval |
17 Jan 2023 |
Tender Closing |
28 Jan 2023 |
Technichal Pre-Qualification |
17 Jan 2023 |
Price bid opening |
27 Jan 2023 |
Approval Dates
Workorder Date |
02 Feb 2023 |
NA |
14 Feb 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Cherpulassery PH Sn AE |
Date: 26/06/2024 |
Work has been completed | 100% Completed
Work Completed. Final Bill Under Preparation..
Cherpulassery PH Sn AE |
Date: 21/06/2024 |
Work has been completed | 100% Completed
Work Completed. Final Bill Under Preparation..