Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work

Project Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work
Project Code PKDJJM09219406P2
Type Package
Main Project JJM 2020 -21 -Supplying, laying, testing, commissioning and mace of distribution system, providing FHTCs (1678nos)and supply & erection of electromagnetic flow meter in Vellinezhi Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JAL JEEVAN MISSION -2020-21- SUPPLYING ,LAYING,TESTING,COMMISSIONING AND MAINTENANCE OF DISTRIBUTION SYSTEM AND PROVING FHTCs -IN VELLINEZHY PANCHAYATH-PHASE II -EXTRA WORK-Pipeline Work
Status On-going
District Palakkad
Executing Office Cherplassery PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 9870000
TS Number TS/16975/2022_26_1_1
Technical specification JJM 2020-2021 Supplying, laying, testing, commissioning and maintenance of distribution system providing FHTCs (1678 Nos) and supply and erection of electromagnetic flow meter in Vellinezhy panchayath-Phase II" is awarded and execution is going on.To complete the house connection awarded in this work it is required to provide additional dstribution network.Hence thisadditional work for street main extention is arranged which include laying of (75mm PVC 8 kg pipe-1320m, 63mm PVC 8 kg pipe-9900m,50mm GI pipe- 1152m,65mm GI pipe -300m) and concrete of LSGD road.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/02/2023
Scheduled date of Completion as per agreement 05 Apr 2023
Expected date of Completion 20/12/2023

Processing Dates

TS Date 12 Jan 2023
Estimate Approval 12 Jan 2023
NIT Approval 17 Jan 2023
Tender Closing 28 Jan 2023
Technichal Pre-Qualification 17 Jan 2023
Price bid opening 27 Jan 2023

Approval Dates

Workorder Date 02 Feb 2023
NA 14 Feb 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Cherpulassery PH Sn AE
Date: 26/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation..

Cherpulassery PH Sn AE
Date: 21/06/2024

Work has been completed | 100% Completed

Work Completed. Final Bill Under Preparation..