| Project | AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work |
|---|---|
| Project Code | KLMAMRUT 2112215324P1 |
| Type | Package |
| Main Project | AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work WSS 2 |
| Funding Agency | AMRUT 2 |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | |
| Description | AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 5816400 |
| TS Number | WRD/KW-CE(SR)/TS/12805/2023_26_1_1 |
| Technical specification | supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) - |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/12/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jun 2024 |
| Expected date of Completion | 06/06/2024 |
| TS Date | 07 Jul 2023 |
|---|---|
| Estimate Approval | 07 Jul 2023 |
| NIT Approval | 14 Jul 2023 |
| Tender Closing | 10 Aug 2023 |
| Technichal Pre-Qualification | 10 Aug 2023 |
| Price bid opening | 27 Jul 2023 |
| Workorder Date | 05 Dec 2023 |
|---|---|
| NA | 12 Dec 2023 |
| Kollam WS Sn 2 - AE |
| Date: 19/01/2026 |
Work has been completed | 100% Completed
Work completed and final bill submitted on 19.12.2025..
| Kollam WS Sn 2 - AE |
| Date: 15/04/2025 |
Work has been completed | 100% Completed
The work has been successfully completed. (Pipe laying (4.03Km),and restoration of concrete is completed).