Kollam WS Sn 2 - AE
Date: 19/01/2026

Work has been completed | 100% Completed

Work completed and final bill submitted on 19.12.2025.

Kollam WS Sn 2 - AE
Date: 15/04/2025

Work has been completed | 100% Completed

The work has been successfully completed. (Pipe laying (4.03Km),and restoration of concrete is completed)

Kollam WS Sn 2 - AE
Date: 09/04/2025

Work in progress | 96% Completed

Pipe laying completed (4.03Km), and restoration of concrete to be completed.

Kollam WS Sn 2 - AE
Date: 05/04/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side

Kollam WS Sn 2 - AE
Date: 29/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side.

Kollam WS Sn 2 - AE
Date: 26/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side.

Kollam WS Sn 2 - AE
Date: 22/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side.

Kollam WS Sn 2 - AE
Date: 18/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side.

Kollam WS Sn 2 - AE
Date: 15/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side.

Kollam WS Sn 2 - AE
Date: 11/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side

Kollam WS Sn 2 - AE
Date: 06/03/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side

Kollam WS Sn 2 - AE
Date: 27/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side

Kollam WS Sn 2 - AE
Date: 22/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side

Kollam WS Sn 2 - AE
Date: 15/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers.

Kollam WS Sn 2 - AE
Date: 10/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers.

Kollam WS Sn 2 - AE
Date: 06/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers.

Kollam WS Sn 2 - AE
Date: 03/02/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers.

Kollam WS Sn 2 - AE
Date: 30/01/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers.

Kollam WS Sn 2 - AE
Date: 28/01/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete is in progress.

Kollam WS Sn 2 - AE
Date: 25/01/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete is in progress.

Kollam WS Sn 2 - AE
Date: 21/01/2025

Work in progress | 95% Completed

Pipe laying completed, and restoration of concrete is in progress.

Kollam WS Sn 2 - AE
Date: 14/01/2025

Work in progress | 83% Completed

2950 m ouot of 3250 m completed, and restoration of concrete is in progress.

Kollam WS Sn 2 - AE
Date: 13/01/2025

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 06/01/2025

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 01/01/2025

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 26/12/2024

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 21/12/2024

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 16/12/2024

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 09/12/2024

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 04/12/2024

Work in progress | 76% Completed

Work progressing

Kollam WS Sn 2 - AE
Date: 30/11/2024

Work in progress | 76% Completed

Work progressing

Kollam WS Sn 2 - AE
Date: 28/11/2024

Work in progress | 76% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 25/11/2024

Work in progress | 75% Completed

2648.7 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 20/11/2024

Work in progress | 69% Completed

2250 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 14/11/2024

Work in progress | 69% Completed

2250 meter pipe laid out of 3250 meter and work ongoing.

Kollam WS Sn 2 - AE
Date: 11/11/2024

Work in progress | 65% Completed

65% Completed 11/11/2024 2141.3m Pipe laid. Work in progress

Kollam WS Sn 2 - AE
Date: 05/11/2024

Work in progress | 65% Completed

2141.3m Pipe laid. Work in progress

Kollam WS Sn 2 - AE
Date: 02/11/2024

Work in progress | 65% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 30/10/2024

Work in progress | 65% Completed

Work in progress

Attached images

img img

Kollam WS Sn 2 - AE
Date: 28/10/2024

Work in progress | 65% Completed

Intermittent heavy rain causes water logged in most of the pipe laying area and affects the progress of work.

Kollam WS Sn 2 - AE
Date: 25/10/2024

Work in progress | 56% Completed

Work delaying due to water logging and heavy rainfall

Kollam WS Sn 2 - AE
Date: 22/10/2024

Work in progress | 56% Completed

Work delaying due to water logging

Kollam WS Sn 2 - AE
Date: 18/10/2024

Work in progress | 56% Completed

Pipe laying in progress.

Kollam WS Sn 2 - AE
Date: 14/10/2024

Work in progress | 56% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 08/10/2024

Work in progress | 56% Completed

Work delayed due to rain

Kollam WS Sn 2 - AE
Date: 04/10/2024

Work in progress | 56% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 30/09/2024

Work in progress | 56% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 26/09/2024

Work in progress | 56% Completed

Work in progress.

Kollam WS Sn 2 - AE
Date: 23/09/2024

Work in progress | 56% Completed

56 % completed , balance in progress.

Kollam WS Sn 2 - AE
Date: 18/09/2024

Work in progress | 55% Completed

work in progress

Kollam WS Sn 2 - AE
Date: 13/09/2024

Work in progress | 55% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 09/09/2024

Work in progress | 50% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 05/09/2024

Work in progress | 50% Completed

Work in progress

Attached images

img

Kollam WS Sn 2 - AE
Date: 02/09/2024

Work in progress | 50% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 29/08/2024

Work in progress | 50% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 24/08/2024

Work in progress | 39% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 22/08/2024

Work in progress | 39% Completed

WORK IN PROGRESS

Attached images

img

Kollam WS Sn 2 - AE
Date: 16/08/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 13/08/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 09/08/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 06/08/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 01/08/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 29/07/2024

Work in progress | 38% Completed

Heavy rainfall delaying the progress of work

Kollam WS Sn 2 - AE
Date: 25/07/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 22/07/2024

Work in progress | 38% Completed

Heavy rainfall delaying the progress of work

Kollam WS Sn 2 - AE
Date: 18/07/2024

Work in progress | 38% Completed

Heavy rainfall delaying the progress of work

Kollam WS Sn 2 - AE
Date: 12/07/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 09/07/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 05/07/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 02/07/2024

Work in progress | 38% Completed

Due to heavy rain and water logging in the Project area work progress is Nil.

Kollam WS Sn 2 - AE
Date: 29/06/2024

Work in progress | 38% Completed

Due to heavy rain and water logging in the Project area work progress is Nil.

Kollam WS Sn 2 - AE
Date: 26/06/2024

Work in progress | 38% Completed

Due to heavy rain and water logging in the Project area work progress is Nil.

Kollam WS Sn 2 - AE
Date: 24/06/2024

Work in progress | 38% Completed

Work delaying due to heavy rain and water logging

Kollam WS Sn 2 - AE
Date: 19/06/2024

Work in progress | 38% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 15/06/2024

Work in progress | 37% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 14/06/2024

Work in progress | 37% Completed

Work in progress

Kollam WS Sn 2 - AE
Date: 10/06/2024

Work in progress | 37% Completed

Due to frequent and heavy rain work progress is slow.

Kollam WS Sn 2 - AE
Date: 05/06/2024

Work in progress | 36% Completed

Due to heavy water logged and land sliding area , pipe laying is difficult.

Kollam WS Sn 2 - AE
Date: 01/06/2024

Work in progress | 36% Completed

Due to heavy and continuous rain work not possible

Kollam WS Sn 2 - AE
Date: 30/05/2024

Work in progress | 36% Completed

36% completed, heavy and continuous rain badly affects the pipe laying works

Kollam WS Sn 2 - AE
Date: 25/05/2024

Work in progress | 36% Completed

Due to heavy and continuous rain work not possible

Kollam WS Sn 2 - AE
Date: 21/05/2024

Work in progress | 36% Completed

Pipe laying work is ongoing . Heavy rain affects the progress of the work.

Kollam WS Sn 2 - AE
Date: 17/05/2024

Work in progress | 35% Completed

Pipe laying work in progress. High atmospheric temperature causes slow progress.

Kollam WS Sn 2 - AE
Date: 13/05/2024

Work in progress | 30% Completed

Pipe laying work in progress. High atmospheric temperature causes slow progress.

Kollam WS Sn 2 - AE
Date: 08/05/2024

Work in progress | 29% Completed

Pipe laying work in progress. High atmospheric temperature causes slow progress.

Kollam WS Sn 2 - AE
Date: 04/05/2024

Work in progress | 26% Completed

Pipe laying work in progress. High atmospheric temperature affects the progress of work.

Kollam WS Sn 2 - AE
Date: 30/04/2024

Work in progress | 21% Completed

Due to heavy drought and high temparature work progress is slow

Kollam WS Sn 2 - AE
Date: 27/04/2024

Work in progress | 21% Completed

Pipe laying is in progress

Kollam WS Sn 2 - AE
Date: 24/04/2024

Work in progress | 20% Completed

Pipe laying is in progress

Kollam WS Sn 2 - AE
Date: 20/04/2024

Work in progress | 19% Completed

Pipe laying in progress

Kollam WS Sn 2 - AE
Date: 16/04/2024

Work in progress | 18% Completed

Pipe laying in progress

Kollam WS Sn 2 - AE
Date: 12/04/2024

Work in progress | 18% Completed

Pipe laying in progress

Kollam WS Sn 2 - AE
Date: 09/04/2024

Work in progress | 17% Completed

Pipe laying in progress

Kollam WS Sn 2 - AE
Date: 01/04/2024

Work in progress | 10% Completed

work in progress, concrete demolishing is needed in almost site.

Kollam WS Sn 2 - AE
Date: 25/03/2024

Work in progress | 9% Completed

Pipe laying works in progress. 350 m Pipe laid.

Kollam WS Sn 2 - AE
Date: 21/03/2024

Work in progress | 9% Completed

Pipe laying works in progress. 300 m Pipe laid.

Kollam WS Sn 2 - AE
Date: 15/03/2024

Work in progress | 9% Completed

Pipe laying work in progress. Almost roads are needed concrete demolishing.

Kollam WS Sn 2 - AE
Date: 11/03/2024

Work in progress | 8% Completed

Pipe laying work in progress

Kollam WS Sn 2 - AE
Date: 06/03/2024

Work in progress | 5% Completed

work started on 2/3/24

Kollam WS Sn 2 - AE
Date: 01/03/2024

Work in progress | 1% Completed

Site inspection ongoing

Kollam WS Sn 2 - AE
Date: 26/02/2024

Work in progress | 1% Completed

Site inspection in progress.

Kollam WS Sn 2 - AE
Date: 21/02/2024

Work in progress | 1% Completed

Site inspection in progress.

Kollam WS Sn 2 - AE
Date: 17/02/2024

Work in progress | 0% Completed

Tested pipe received, Work will start next day.

Kollam WS Sn 2 - AE
Date: 14/02/2024

Work in progress | 0% Completed

Work will start soon after getting tested pipe.

Kollam WS Sn 2 - AE
Date: 12/02/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 06/02/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 02/02/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 29/01/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 23/01/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 20/01/2024

Work in progress | 0% Completed

Tested pipe not get

Kollam WS Sn 2 - AE
Date: 16/01/2024

Work in progress | 0% Completed

Handed over the site, Tested pipe not get.

Kollam WS Sn 2 - AE
Date: 09/01/2024

Work in progress | 0% Completed

Handed over the site

Kollam WS Sn 2 - AE
Date: 06/01/2024

Work in progress | 0% Completed

LOA submitted and agreement executed. Site hand over not done, because the contractor not uploaded digitally signed SHO proforma.

Kollam WS Sn 2 - AE
Date: 03/01/2024

Work in progress | 0% Completed

LOA submitted and agreement executed. Site hand over not done, because the contractor not uploaded digitally signed SHO proforma.

Kollam WS Sn 2 - AE
Date: 29/12/2023

Work has started | 0% Completed

LOA submitted. Agreement executed on 12/12/23 vide agreement No 12/2023-24/EE/PHDNK