JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II

Project JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II
Project Code TVMJJM02229779
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM: CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II - Supplying, conveying, laying, testing and commissioning of distribution network and providing 15438 Nos FHTCs
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 891714000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 877910000
TS Number TS/2022-2023/2021/19469
Total Bill Submitted (Rs) 231917422
Total Bill Paid (Rs) 54273773
Population Benefitted 89465
Capacity in MLD 18.00
Actual Project Completion Date 04 May 2024
Coverage This project envisages providing distribution network from OHSRs and sump proposed for the scheme in Phase-I and providing FHTCs (15348 Nos.) to households of all the three panchayaths - Pulimath, Nagaroor and Karavaram under Jala Jeevan Mission
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II - Supplying, conveying, laying, testing and commissioning of distribution network and providing 15438 Nos FHTCs Trivandrum Project Dn
2 JJM: CWSS to Pulimath, Nagaroor, Karavaram Panchayaths, Phase-II-Supplying and laying distribution line and FHTCs from Kadavila junction to Kattaparambu road in Nagaroor panchayath Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2024 4450 house connections and 138km PVC pipe laid till date. Around 1.5km of DI pipe laid. Overall progress of the work is very slow despite repeated directions given for increasing the pace of work. Due to non supply of DI pipes and other required materials of work, work cannot be completed at many locations. Pending works are there for the pipe laid portions. Thiruvananthapuram Project AE3
08 Nov 2023 Work progress is very slow. Supply of DI pipes not yet started despite various site instructions. Supply of valves and other items in work schedule not done. FHTCs progress is also very slow. Thiruvananthapuram Project AE3
22 Sep 2023 Progress of the work is slow despite repeated site instructions for supply of DI pipes, valves and other items in the work as per schedule. Progress of FHTCs in the work has not been improved despite several instructions given for increasing the labour for providing FHTCs/HTCs. Thiruvananthapuram Project AE3
22 Apr 2023 Work of laying distribution lines started in all three panchayaths of Pulimath, Nagaroor and Karavaram. Around 100km of PVC pipes supplied. Thiruvananthapuram Project AE3
12 Mar 2023 Eventhough FHTCs work started at Karavaram GP in two roads, where immediate tarring is scheduled by panchayath, work is in slow phase. Contractor not supplying the pipes after repeated instructions and letter given, and labour force and supervisors not allotted by the contractor for increasing the pace of work. Thiruvananthapuram Project AE3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/04/2022
Scheduled date of Completion of the Project 04 May 2024
Expected date of Completion 04/05/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 11 Apr 2022

Other details

Project Officers View