JJM: CWSS to Pulimath, Nagaroor, Karavaram Panchayaths, Phase-II-Supplying and laying distribution line and FHTCs from Kadavila junction to Kattaparambu road in Nagaroor panchayath

Project JJM: CWSS to Pulimath, Nagaroor, Karavaram Panchayaths, Phase-II-Supplying and laying distribution line and FHTCs from Kadavila junction to Kattaparambu road in Nagaroor panchayath
Project Code TVMJJM02229779P2
Type Package
Main Project JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description The road widening and restoration works of Kadavila Jn-Kattaparambu road in Nagaroor panchayath has already started by Thiruvananthapuram District panchayath. Distribution line available in the stretch has to be extended and FHTCs need to be provided in the stretch before the completion of road restoration works on urgent basis, since the road will be under DLP for 5 years after completion of tarring works.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 6514000
TS Number 8765/2022-2023
Technical specification The road widening and restoration works of Kadavila Jn-Kattaparambu road in Nagaroor panchayath has already started by Thiruvananthapuram District panchayath. Distribution line available in the stretch has to be extended and FHTCs need to be provided in the stretch before the completion of road restoration works on urgent basis, since the road will be under DLP for 5 years after completion of tarring works.
Contractor Sasidaran Nair (Mob: 9847478343)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/12/2022
Scheduled date of Completion as per agreement 30 Jun 2023
Expected date of Completion 31/03/2023

Processing Dates

TS Date 17 Dec 2022
Estimate Approval 17 Dec 2022
NIT Approval 21 Dec 2022
Tender Closing 31 Dec 2022
Technichal Pre-Qualification 31 Dec 2022
Price bid opening 02 Jan 2023

Approval Dates

NA 22 Feb 2023
Workorder Date 06 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE3
Date: 17/07/2023

Work has been completed | 100% Completed

Laying of PVC distribution lines and FHTCs completed. .

Thiruvananthapuram Project AE3
Date: 15/07/2023

Work in progress | 96% Completed

Laying of PVC distribution lines of all sizes completed. Hydrostatic pressure test completed for the PVC distribution lines laid. Work of providing FHTCs ongoing. 241 FHTCs provide..